Town of Southport is a town in Chemung County, New York. Town of Southport adopts its own zoning, so inside its limits Town of Southport’s rules apply, not the county’s. 7 rules below are quoted from official sources and independently re-checked, most recently on October 23, 2026. Rules for unincorporated land are on the Chemung County page.

Answers from the rulebook for Town of Southport

Town of Southport’s own rules

  • Building permitRequired

    Work inside Southport that must conform to the Uniform Code or Energy Code, including residential construction, enlargement, alteration, improvement, removal, relocation, demolition, and specified solid-fuel heating work.

    • Exempt categories include a qualifying one-story detached shed, playhouse, or similar structure of no more than 144 square feet; specified playground equipment; entirely aboveground pools designed for water depth below 24 inches; agricultural fences; certain retaining walls; temporary sets and scenery; qualifying window awnings; low partitions or movable cases; finish work; listed portable equipment or appliances; specified replacement equipment; and repairs without fire- or life-safety impact.
    • An exemption does not authorize noncompliant work.
    • An application must be made in writing by the owner or authorized agent, with information and documents required by § 245-4D.
    • Work may not begin unless a permit is issued.
    • A permit becomes invalid if authorized work is not commenced within six months, expires 12 months after issuance, and may be renewed upon application, applicable fee payment, and Code Enforcement Officer approval.

    detached exempt structure gross floor area: <= 144 square feet (One-story detached structure associated with specified dwellings and used for tool/storage sheds, playhouses, or similar uses.) · permit commencement deadline: <= 6 months (Permit otherwise becomes invalid.) · permit expiration: 12 months (Measured after issuance.)

    “Building permits required. Except as otherwise provided in Subsection B of this section, a building permit shall be required for any work which must conform to the Uniform Code and/or the Energy Code, including, but not limited to, the construction, enlargement, alteration, improvement, removal, relocation, or demolition of any building or structure or any portion thereof, and the installation of a solid-fuel-burning heating appliance, chimney, or flue in any dwelling unit.”
  • InspectionsRequired

    Permitted construction work inside Southport, where the listed element of work is applicable.

    • Work must remain accessible and exposed until inspected and accepted.
    • The permit holder must notify the Code Enforcement Officer when listed work is ready for inspection.
    • Remote inspection may substitute only at the Code Enforcement Officer's or authorized inspector's discretion and only if it provides the required information and quality; otherwise an in-person inspection is required.
    • The applicable inspection fee must be paid before or when each inspection occurs.
    “Work shall remain accessible and exposed until inspected and accepted by the Code Enforcement Officer or by an inspector authorized by the Code Enforcement Officer. The permit holder shall notify the Code Enforcement Officer when any element of work described in Subsection B of this section is ready for inspection.”
  • Local zoningPresent (with conditions)

    Land inside the Town of Southport.

    • The chapter was amended in its entirety on March 8, 2016; subsequent amendments are noted where applicable.
    “[HISTORY: Adopted by the Town Board of the Town of Southport 8-27-1946; amended in its entirety 3-8-2016 by L.L. No. 1-2016 (Res. No. 1-2016). Subsequent amendments noted where applicable.]”
  • Agricultural exemptionConditional

    Agricultural fencing inside Southport.

    • The exemption is limited to installation of a fence for agricultural use as defined by the New York State Agriculture and Markets Law.
    • The exemption does not authorize work that violates the Uniform Code or Energy Code.
    “Installation of fence for agricultural use, as defined by the New York State Agriculture and Markets Law;”
  • Subdividing landRegulated (with conditions)

    Subdivision of land inside Southport.

    • The detailed approval standards, exemptions, and process require review of Chapter 464.
    “Chapter 464 Subdivision of Land (§ 464-1 – § 464-35)”
  • Permit feesVariable (with conditions)

    Town code-enforcement permits and inspections inside Southport.

    • Fees are set by the Town Board.
    • The applicable permit fee must be paid when submitting an application for a building permit, amended permit, or renewal.
    • The applicable inspection fee must be paid prior to or at the time of each inspection.
    “To collect fees as set by the Town Board of this Town;”
  • Permit processPublished (with conditions)

    Building-permit applications inside Southport.

    • The application must be in writing on a form provided by or acceptable to the Code Enforcement Officer.
    • The application must be signed by the property owner or the owner's authorized agent.
    • The application must provide sufficient information for the Code Enforcement Officer to determine code compliance, including the listed documents in § 245-4D.
    • Work may not commence until a building permit is issued.
    “Applications for a building permit shall be made, in writing, on a form provided by or otherwise acceptable to the Code Enforcement Officer. The application shall be signed by the owner of the property where the work is to be performed or an authorized agent of the owner.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Town of Southport or Chemung County directly.

  • Owner-builder exemption — Owner-performed residential construction inside Southport.
  • Certificate of occupancy — Occupancy of buildings or structures inside Southport.
  • Minimum dwelling size — Single-family dwellings inside Southport.
  • Living in an RV — Residential occupancy of recreational vehicles on private land inside Southport.
  • Camping on your land — Temporary camping on private land inside Southport.
12 more unanswered
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Who permits septic
  • Septic permit
  • Septic inspection
  • Off-grid sanitation
  • Well permit
  • Mandatory utility hookup
  • Driveway access
  • Building in a floodplain
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Town of Southport publishes no rule on the point, not that none exists. Chemung County’s page lists the county offices to call.

Off-grid gear

Going off-grid in Town of Southport means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

← All of Chemung County: county rules, score and offices