Building in the Borough of Oakland, Bergen County, New Jersey takes a construction permit from the borough's construction official under the state Uniform Construction Code1 and a zoning permit from the Zoning Enforcement Official2. Oakland adopts and enforces its own zoning3, and septic systems are permitted through the Oakland Board of Health4.
At a glance
- Building permit
- Required; issued by the Oakland construction official under the state Uniform Construction Code15
- Zoning permit
- Required before building or changing a land use; issued by the Zoning Enforcement Official2
- Zoning
- Oakland zones its own land by district; Bergen County does not set municipal zoning36
- Septic permit
- Required; issued by the Oakland Board of Health to a licensed septic installer47
- New septic system permit fee
- $525 (alteration $350)7
- Minimum home size
- Set by district in Schedule D of the zoning chapter8
- Owner-builder
- State rule: an owner building a home for personal use files an affidavit with the construction official before a certificate of occupancy9
- RV and tiny home living
- Not confirmed; ask the Zoning Officer3
Who to call
Building permits
Borough of Oakland Construction and Code Enforcement (Construction Official)
Plan review, inspections and enforcement of the Uniform Construction Code for construction inside Oakland
One Municipal Plaza, Oakland, NJ 07436
Zoning
Borough of Oakland Zoning Officer (Construction and Code Enforcement)
Zoning review and zoning permits for construction, sheds, fences, signs and driveway expansions inside Oakland
One Municipal Plaza, Oakland, NJ 07436
Septic permits
Borough of Oakland Health Department (septic plan reviews and permits)
Septic plan reviews, septic repair permit applications and septic permit packets for Oakland
One Municipal Plaza, Oakland, NJ 07436
Contact details are copied from each office’s official page and were checked against it on October 13, 2026.
Off-grid gear
Going off-grid in Borough of Oakland means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Oakland, NJ?
Yes. New Jersey requires a construction permit before a building is built, enlarged, altered or demolished1, and in Oakland that permit comes from the borough's own construction office, which handles plan review and inspections for residential, commercial and industrial work5. Ordinary maintenance is the main exception10.
A second approval sits in front of the construction permit: the Oakland zoning chapter says no building may be erected, altered or demolished unless it conforms to the district rules and the owner or contractor first obtains a zoning permit from the Zoning Enforcement Official2. A new house, a shed over 200 square feet or an addition to a house carries a $100 zoning permit fee11. Plan on both permits for any real project.
Who issues building and zoning permits in Oakland, and how do you reach them?
Oakland handles both in-house, from One Municipal Plaza. The Construction Official's office handles building permits and inspections under the Uniform Construction Code5; call (201) 337-8111 ext. 2021. The Zoning Officer reviews zoning applications and issues zoning permits11; call 201-337-8111, ext. 2022.
Bergen County's offices are not the right counter for a lot inside Oakland. Bergen County does not set municipal zoning, which stays with the municipality6. Oakland's inspectors also schedule inspections for open building permits through the borough's online portal5.
Does Oakland have zoning, and what does it mean for setbacks and lot size?
Yes. Oakland divides the borough into zoning districts and regulates the use of land through its own zoning ordinance, Chapter 59, Article VII3. Where two rules conflict, the most restrictive lawful rule governs3.
Lot size, yards and building height are set district by district in Schedule A of that chapter, so the answer depends on the zone your parcel sits in12. In residential zones the front yard follows Schedule A, but it may match the average of the existing front yards on the block, and never less than 30 feet on blocks with under 1,000 feet of frontage13. A new dwelling must also meet the minimum floor area for its district in Schedule D8. The Zoning Officer can tell you the district and the numbers for a specific lot11.
How do septic permits work in Oakland?
Septic permits inside Oakland are a borough matter: the Oakland Board of Health regulates individual sewage disposal systems, and construction permits go only to a septic installer licensed by the Oakland Board of Health4. A permit for a new system costs $525 and an alteration costs $350, with a further $100 monitoring fee when the system includes an alternative waste treatment unit7. A failed or repeated inspection can add $100 per hour or part of an hour14.
The designing engineer submits the plan, and every submission must arrive as one complete packet with its fees15. State code allows 30 days for plan review, and submissions are handled in order received15. Systems may not be backfilled until the Board of Health or its designated representative has inspected them4.
Can you live in an RV or tiny home in Oakland, NJ?
We could not confirm an Oakland rule that answers this. The borough's code materials we reviewed did not resolve tiny-home occupancy or temporary camping on private land, so neither is confirmed as allowed or prohibited. Because zoning is set by district3, ask the Oakland Zoning Officer at 201-337-8111, ext. 2022 before buying land or moving anything onto it11. A tiny home built as a permanent dwelling would also need the construction permit and zoning permit described above2.
Building a home in Oakland: the steps, in order
- Ask the Zoning Officer which district the lot is in and what yards, lot size and minimum floor area apply1211.
- If the lot is served by septic, have an engineer prepare the plan and submit it to the Oakland health department with fees in one packet15.
- Apply for the zoning permit from the Zoning Enforcement Official before work starts2.
- Apply to the construction official for the construction permit and book inspections through the borough's online portal5.
- Before a new owner-built home is occupied, file the owner's affidavit with the construction official as the state requires for a certificate of occupancy9.
What stays with Bergen County, and what to check before you buy in Oakland
Outside the borough's own offices, Bergen County keeps the land-development review that touches county roads and drainage. A subdivision that abuts a County road or County drainage facility needs County Planning Board approval, and other subdivisions must still obtain an exemption from the board16. A driveway onto a Bergen County road has its own review, with a $250 road-access permit fee17; a driveway onto a state highway needs a state permit18.
For the county's wider picture, see the Bergen County page. Check the flood hazard map too: development in an Oakland flood hazard area without an issued permit is a violation19. Property taxes are heavy: Bergen County's effective rate is about 1.7%20.
Watch-outs
- Oakland's building and zoning offices are separate approvals: a construction permit does not replace the zoning permit from the Zoning Enforcement Official2.
- We could not confirm Oakland's short-term rental rules; ask the Zoning Officer before planning rental income11.
- Septic permits go only to septic installers licensed by the Oakland Board of Health, so hire from the borough's licensed list4.
- We could not confirm Oakland rules on private wells, accessory dwelling units, or utility-connection requirements; ask the construction official or Zoning Officer5.
Sources
- N.J.A.C. 5:23-2.14, Construction permits—when required (New Jersey statewide rule), quoted and re-checked
- Borough of Oakland, NJ, Chapter 59, Article X: Interpretation; Enforcement; Zoning Permits; Certificates of Occupancy; Fees (Borough of Oakland), quoted and re-checked
- Borough of Oakland, NJ, Chapter 59, Article VII: Zoning (Borough of Oakland), quoted and re-checked
- Borough of Oakland, NJ, Chapter BH6: Individual Sewage Disposal Systems (Borough of Oakland), quoted and re-checked
- Borough of Oakland Construction and Code Enforcement (Construction Official) (oakland-nj.gov)
- Bergen County Standards for Sustainable Land Development—Site Plans, quoted and re-checked
- Borough of Oakland, NJ, Chapter BH6: Individual Sewage Disposal Systems (Borough of Oakland), quoted and re-checked
- Borough of Oakland, NJ, Chapter 59, Article VII: Zoning (Borough of Oakland), quoted and re-checked
- N.J.A.C. 5:23, Uniform Construction Code (New Jersey statewide rule), quoted and re-checked
- The New Jersey State Uniform Construction Code, quoted and re-checked
- Borough of Oakland Zoning Officer (Construction and Code Enforcement) (oakland-nj.gov)
- Borough of Oakland, NJ, Chapter 59, Article VII: Zoning (Borough of Oakland), quoted and re-checked
- Borough of Oakland, NJ, Chapter 59, Article VII: Zoning (Borough of Oakland), quoted and re-checked
- Borough of Oakland, NJ, Chapter BH6: Individual Sewage Disposal Systems (Borough of Oakland), quoted and re-checked
- Borough of Oakland Health Department (septic plan reviews and permits) (oakland-nj.gov)
- Bergen County Standards for Sustainable Land Development—Subdivisions, quoted and re-checked
- Fee Schedule for Site Plan Application, quoted and re-checked
- Major Access Permits (New Jersey statewide rule), quoted and re-checked
- Borough of Oakland, NJ, Chapter 14: Flood Damage Prevention (Borough of Oakland), quoted and re-checked
- Effective property tax rate: Bolthole Index county data
Written October 13, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.