The Village of Old Field, in Suffolk County, New York, runs its own zoning and requires a village building permit for most construction12. The whole village is one residence district with a minimum of two acres per dwelling34. Living in a camper or mobile home is prohibited5. Septic approval comes from Suffolk County's Office of Wastewater Management, not the village6.
At a glance
- Building permit
- Required from the village for most construction; a structure of 100 square feet or less with no foundation is exempt2
- Zoning
- Village zoning ordinance; one residence district covers the whole village13
- Minimum lot size
- Two acres per dwelling4
- Septic
- Suffolk County Office of Wastewater Management approval for new homes6
- RV living
- Prohibited; storage only in a garage or screened rear yard5
- Mobile homes
- Occupancy prohibited7
- Short-term rentals
- Rentals under six consecutive months need Board of Trustees permission8
- Flood zones
- Floodplain development permit with a $500 application fee9
Who to call
Building permits
Village of Old Field Building Department
Building permits, site plans and zoning applications inside Old Field village
Septic permits
Suffolk County Department of Health Services - Office of Wastewater Management
Permits to construct, alter or repair onsite sewage disposal (septic) systems countywide under Article 6 of the Suffolk County Sanitary Code
360 Yaphank Avenue, Suite 2B, Yaphank, NY 11980
Contact details are copied from each office’s official page and were checked against it on October 23, 2026.
Off-grid gear
Going off-grid in Village of Old Field means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Does Old Field, NY have zoning, and what does it mean for lot size and setbacks?
The Village of Old Field adopted its own zoning ordinance, and the entire village is a single district for residences and compatible uses13. Suffolk County itself has no direct zoning power, so the village, not the county, decides what can be built on a lot in Old Field10.
Because there is only one district, the same numbers apply village-wide. Each dwelling needs at least two acres of lot area, which excludes land in or opposite streets and submerged or tidal land4. A street-fronting dwelling needs a front yard of at least 60 feet, a rear yard of at least 75 feet, and side yards totaling at least 75 feet with neither under 25 feet11. Buildings may cover no more than 10% of the lot12, and a main building may not exceed 35 feet in height, or 25 feet for accessory buildings13.
Creating a new lot is a separate step: the Old Field Planning Board must approve a subdivision before any part of it is sold14.
Do you need a building permit in Old Field, and who issues it?
Yes. The Village of Old Field enforces the New York State Uniform Fire Prevention and Building Code, and a village building permit is required for construction, enlargement, alteration, removal, relocation or demolition of a building152. The one stated exception is a structure of 100 square feet or less with no foundation or permanent attachment, which still needs a survey or plot plan, and plumbing still needs a permit2.
Permits come from the village, not Suffolk County. Applications go to the Village of Old Field Building Department, which accepts new applications on Mondays between 12 Noon and 3 PM and on Saturdays by appointment, and the Board of Trustees approves permits at its monthly meetings16. Applications are written on a Village Clerk form, must be signed by the owner, and need plans prepared by a New York State registered architect or professional engineer17. Fees are set by Board of Trustees resolution and double if work starts before the permit is issued18.
The work is inspected at stages from foundation through final, and a certificate of occupancy or compliance follows permitted work1920.
How do septic permits work in Old Field?
Septic permits are not issued by the village. Suffolk County's Department of Health Services, through its Office of Wastewater Management, requires a permit for a new home or business anywhere in the county6. For a new or modified home inside Old Field, the county's residential permits page says approval may be needed to confirm the system meets the Suffolk County Sanitary Code21.
The county grants approval to construct first, then an inspection must be requested before the system is used22. New or expanded single-family residences may be required to install an innovative/alternative onsite system under Article 623. Permits are good for three years after approval to construct24.
Soil matters too: only about 1.2% of Suffolk County soils rate as not limited for a conventional drain field, so expect a site evaluation and possibly an engineered system25. Call the Office of Wastewater Management26. We could not confirm whether the village has a separate rule for private wells; ask the Building Department.
Can you live in an RV or tiny home in Old Field?
No. The Village of Old Field prohibits the use of campers and automobile trailers designed for human habitation, and mobile homes, on any part of a lot57. Storage or parking is allowed only inside a private garage or behind a Board of Trustees-approved screening enclosure in the rear yard, and that exception does not allow anyone to live in the unit5.
We could not confirm how the village treats tiny homes: its code does not define them, so a tiny home would have to meet the zoning and building permit rules for a dwelling, including the two-acre lot requirement4. Ask the Building Department before buying. Rentals are also tight: leases shorter than six consecutive months need Board of Trustees permission, granted only for severe, non-self-created financial hardship8.
Building a home in Old Field: the steps, in order
- Confirm the lot has at least two acres of qualifying area and fits the setbacks411.
- If the lot is new or being split, get Planning Board subdivision approval first14.
- Check whether the lot is in a special flood hazard area; if so, a floodplain development permit with a $500 application fee is also required9.
- Start septic review with Suffolk County's Office of Wastewater Management626.
- Have a New York State registered architect or professional engineer prepare plans, then file the application with the Village Clerk form through the Building Department1716.
- Wait for Board of Trustees approval at its monthly meeting16.
- Keep work exposed until each inspection is passed, then request the certificate of occupancy1920.
What stays with Suffolk County, and what to check before you buy in Old Field?
The village decides zoning, building permits and subdivisions inside its limits. Suffolk County decides septic approval and subdivision water-supply and sewage review627. For land outside the village, see the Suffolk County page, because the village's rules do not apply there.
Before buying, check these:
- Lot area counts only buildable land, so submerged or tidal ground does not count toward the two acres4.
- Flood maps decide whether a floodplain permit is needed9.
- Suffolk County's effective property tax rate is 1.9% and its median property tax bill is $10,001 per year2829.
- Typical home values in Suffolk County are about $726,69230.
Watch-outs
- Contractors and applicants should confirm timing: the Board of Trustees approves building permits at monthly meetings, so a complete application can still wait for the next meeting16.
- Old Field's two-acre minimum, 10% lot coverage cap and 75-foot rear yard make small or odd-shaped lots hard to build on, so confirm buildable area before closing41211.
- We could not confirm an owner-builder exemption, a private-well permit rule, or tiny-home treatment inside the village; ask the Old Field Building Department at 631-941-944916.
Sources
- Article I: General Provisions - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Article X: Administration, Permits and Enforcement - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Article I: General Provisions - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- ecode360.com (Village of Old Field), quoted and re-checked
- Article II: Permitted and Prohibited Uses - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Wastewater Management, quoted and re-checked
- Article II: Permitted and Prohibited Uses - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Article II: Permitted and Prohibited Uses - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Chapter 44: Flood Damage Prevention - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Suffolk County Planning Commission Minutes: November 5, 2003, quoted and re-checked
- ecode360.com (Village of Old Field), quoted and re-checked
- Article IV: General Area Requirements - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- ecode360.com (Village of Old Field), quoted and re-checked
- Chapter 95: Subdivision of Land - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Article I: General Provisions - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Village of Old Field Building Department (oldfieldny.org)
- Article X: Administration, Permits and Enforcement - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Article X: Administration, Permits and Enforcement - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- Article X: Administration, Permits and Enforcement - Village of Old Field, NY (Village of Old Field), quoted and re-checked
- NYS Uniform Fire Prevention and Building Code: What Elected Officials Need to Know, quoted and re-checked
- Suffolk County Department of Health Services — Residential Permits (Village of Old Field), quoted and re-checked
- Wastewater Management, quoted and re-checked
- Suffolk County Sanitary Code Article 6, quoted and re-checked
- Wastewater Management, quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- Suffolk County Department of Health Services - Office of Wastewater Management (suffolkcountyny.gov)
- suffolkcountyny.gov, quoted and re-checked
- Effective property tax rate: Bolthole Index county data
- Median property tax bill: Bolthole Index county data
- Typical home value (Zillow): Bolthole Index county data
Written October 23, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.