Lamar Township, Clinton County, Pennsylvania has its own zoning ordinance, and the township zoning officer issues a zoning permit before any building or addition is started12. Clinton County's zoning ordinance does not cover the township3. Building code (UCC) permits follow state law, and septic permits come from a local agency, which we could not confirm for Lamar45.

At a glance

Zoning
Yes, township Chapter 27, enforced by the township zoning officer1
Zoning permit
Required before building, extending or altering any building, including accessory buildings2
Occupancy permit
Required before using or occupying a permitted structure6
Building code (UCC) permit
Required for residential construction under state law; township enforcement arrangement not confirmed4
Septic
Permit from a local agency; Lamar's agency not confirmed5
Private well
No statewide permit for a homeowner drilling their own well7
Clinton County zoning
Does not apply in Lamar Township3

Who to call

Zoning

Lamar Township office (zoning officer)

Township zoning permits, occupancy permits and the zoning hearing board

(570) 726-4973

lamartwp@comcast.net

148 Beagle Road, Mill Hall, PA 17751

Planning & zoning

Clinton County Planning, Zoning, Engineering, Grants

County zoning permits in six other townships; points builders to their municipality or a certified third-party inspector for building permits

570-893-4080

planning@clintoncountypa.gov

2 Piper Way, Suite 244, Lock Haven, PA 17745

Contact details are copied from each office’s official page and were checked against it on October 14, 2026.

Off-grid gear

Going off-grid in Lamar Township means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Does Lamar Township, PA have zoning, and what does it mean for building?

Lamar Township has its own zoning, set out in Chapter 27 of the township code, with the zoning officer and board of supervisors administering it1. The code's general rule is that no building or structure may be built, extended or used except for the purposes the chapter permits1.

Clinton County's zoning ordinance covers only six other townships, so the county's lot, setback and mobile-home standards do not apply in Lamar3. Lamar's own district rules for lot size, setbacks, RVs, tiny homes and manufactured homes are the ones that matter, and we could not confirm them here. Ask the Lamar Township office8 for the zoning map and district regulations before you buy.

Do you need a building permit in Lamar Township, and who issues it?

Yes. Lamar Township requires a zoning permit from the zoning officer before anyone excavates, constructs or alters any building, accessory buildings included2. Repair, maintenance and interior remodeling that does not change the use need no permit, the zoning officer must get at least 24 hours' notice before work starts, and a permit lapses if work has not begun within 1 year2.

That is the zoning permit. A separate Uniform Construction Code permit is required for residential construction under state law4, and Clinton County does not issue it: building permits come from the local municipality or a certified third-party inspector9. Which one handles Lamar we could not confirm, so ask the township office8.

What happens after the permit: inspection and occupancy in Lamar Township?

The township zoning officer inspects completed work for conformity with the zoning chapter, within 10 days of being told the work is done10. Using or occupying a structure that needed a permit is unlawful until the zoning officer issues an occupancy permit, applied for at the same time as the zoning permit for new buildings6.

Permit fees are set by resolution of the board of supervisors, and no permit issues until they are paid11. Applications go on the zoning officer's form with a scale plot plan; a rejected applicant may appeal to the zoning hearing board12. Separate state rules also require a certificate of occupancy for residential buildings built under the UCC13.

How do septic permits and wells work in Lamar Township?

In Clinton County, on-lot septic permits are issued by a local agency, which may be a municipality, a group of municipalities or a county health department14. Which agency serves Lamar Township we could not confirm; the township office8 can name its sewage enforcement officer.

Clinton County's soils make this step matter: only about 10% of soils are rated not limited for a conventional drain field, so expect a site evaluation and possibly an engineered system15. A homeowner who drills their own well on their own land does not need the driller's license and permits that apply to drilling companies, and the state has no construction standards for private wells, though some municipalities set their own716.

Building a home in Lamar Township: the steps, in order

  1. Call the Lamar Township office for the zoning map, district regulations and the sewage enforcement officer's name8.
  2. Get septic site testing and a permit from the local agency before designing the house5.
  3. Apply for the zoning permit with a plot plan and fee1211.
  4. Obtain the residential UCC permit from the municipality or a certified third-party agency4.
  5. Give the zoning officer notice before starting2.
  6. Request the zoning inspection and occupancy permit when work is done106.

A driveway onto a state road needs a PennDOT highway occupancy permit17.

Watch-outs

  • Lamar Township's district rules for lot size, setbacks, RVs, tiny homes and manufactured homes were not confirmed; get them from the township zoning officer before you buy8.
  • Do not rely on Clinton County's zoning ordinance for Lamar parcels; it covers six other townships3.
  • Activity in or near streams, floodways or wetlands in Clinton County usually needs a state-level permit, even where the township asks for none18.
  • Pennsylvania's recreational-cabin exclusion from the UCC is narrow and is not a general owner-builder exemption19.

Sources

  1. Lamar Township Code, Chapter 27 Zoning, Parts 12-14 (enforcement, permits) (Lamar Township), quoted and re-checked
  2. Lamar Township Code, Chapter 27 Zoning, Parts 12-14 (enforcement, permits) (Lamar Township), quoted and re-checked
  3. Ordinances & Maps | Clinton County, PA, quoted and re-checked
  4. PART XIV, quoted and re-checked
  5. Municipal On-Lot Sewage Service Areas, quoted and re-checked
  6. Lamar Township Code, Chapter 27 Zoning, Parts 12-14 (enforcement, permits) (Lamar Township), quoted and re-checked
  7. Private Water Wells, quoted and re-checked
  8. Lamar Township office (zoning officer) (lamartownship.com)
  9. Clinton County Planning, Zoning, Engineering, Grants (clintoncountypa.gov)
  10. Lamar Township Code, Chapter 27 Zoning, Parts 12-14 (enforcement, permits) (Lamar Township), quoted and re-checked
  11. Lamar Township Code, Chapter 27 Zoning, Parts 12-14 (enforcement, permits) (Lamar Township), quoted and re-checked
  12. Lamar Township Code, Chapter 27 Zoning, Parts 12-14 (enforcement, permits) (Lamar Township), quoted and re-checked
  13. pa.gov, quoted and re-checked
  14. Municipal On-Lot Sewage Service Areas, quoted and re-checked
  15. Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
  16. Private Water Wells, quoted and re-checked
  17. Apply for a PennDOT Highway Occupancy Permit, quoted and re-checked
  18. Do I Need a Permit?, quoted and re-checked
  19. pa.gov, quoted and re-checked

Written October 14, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Lamar Township

Lamar Township’s own rules

  • Building permitRequired

    Excavation, construction or alteration of any building, including accessory buildings, inside Lamar township (township zoning permit)

    • No permit required for repair, maintenance or interior remodeling that does not change the use or otherwise violate chapter 27
    • Permit expires after 1 year if work has not commenced; all work must be completed within 2 years
    • Zoning officer must be given at least 24 hours notice before work starts
    • This is the zoning permit; a separate building code (UCC) permit was not verified

    permit expiry if work not started: 1 year · work completion deadline: 2 years

    “it shall be unlawful to commence the excavation, construction or alteration of any building, including an accessory building, until the zoning officer has issued a zoning permit for such work.”
  • InspectionsLimited

    Zoning-conformity inspection of completed work inside Lamar township by the township zoning officer

    • Inspection is for conformity with chapter 27 zoning; building-code inspections were not verified

    inspection timeframe after completion notice: <= 10 days

    “the zoning officer shall inspect any structure, building, sign and/or use of land within 10 days of notification that the work has been completed.”
  • Certificate of occupancyRequired

    Use or occupancy of structures or land for which a permit is required inside Lamar township (township occupancy permit)

    • Application for occupancy permit is made at the same time as the zoning permit for new buildings or additions
    • Zoning officer inspects within 10 days of completion notice
    “it shall be unlawful to use and/or occupy any structure, building, sign and/or land or portion thereof for which a permit is required until an occupancy permit has been issued by the zoning officer.”
  • Local zoningPresent

    Land inside Lamar township; Chapter 27 Zoning of the township code, administered by the township zoning officer and board of supervisors

    • Chapter 27 has Parts 1-16 including zoning districts, district regulations, zoning hearing board and zoning map amendments
    “unless otherwise provided by law or in this chapter no building or structure shall be constructed, erected, or extended, and no building, structure or land shall be used or occupied, except for the purposes permitted herein.”
  • Permit feesVariable (with conditions)

    Zoning permits inside Lamar township

    • Fees set by resolution of the board of supervisors; additional fees at township discretion for review of large scale land development
    • Amounts not retrieved; the code library lists a fee schedule
    “no permit shall be issued until the applicable fee(s) have been paid. a schedule of fees have been established by resolution of the board of supervisors.”
  • Permit processPartial

    Zoning permit application and review inside Lamar township

    • Application on form prescribed by zoning officer with plot plan drawn to scale and fee
    • Rejected applicants may appeal to the zoning hearing board
    “when the zoning officer is satisfied that the proposed work and/or use conforms to the provisions of this chapter and all laws and ordinances applicable thereto, he shall issue a permit.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Lamar Township or Clinton County directly.

  • Owner-builder exemption — Owner-builder exemption in Lamar township
  • Building code adopted — Building code in Lamar township
  • Zoning districts — Zoning districts in Lamar township
  • Minimum dwelling size — Minimum dwelling size in Lamar township
  • Minimum lot size — Minimum lot size in Lamar township
19 more unanswered
  • Setbacks
  • Lot coverage
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Who permits septic
  • Septic permit
  • Septic inspection
  • Off-grid sanitation
  • Well permit
  • Mandatory utility hookup
  • Agricultural exemption
  • Subdividing land
  • Driveway access
  • Building in a floodplain
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Lamar Township publishes no rule on the point, not that none exists. Clinton County’s page lists the county offices to call.

← All of Clinton County: county rules, score and offices