South Salt Lake, Utah sets its own zoning under Title 171 and requires a city building permit for most construction, including new buildings, additions and remodels2. Septic permits are a different office: the Salt Lake County Health Department reviews and permits new onsite wastewater systems countywide, city or not3. Rules for unincorporated Salt Lake County do not apply inside city limits.
At a glance
- Zoning
- Set by the city (Title 17 Land Use Ordinance)1
- Building permit
- Required for most construction; some minor work is exempt2
- Inspections
- Every building permit requires an inspection4
- Septic permits
- Salt Lake County Health Department3
- Accessory dwellings
- Allowed in the R1 and RM districts only5
- Owner-builder
- Exempt from contractor licensing, but permits and inspections still apply6
Who to call
Building permits
South Salt Lake Community Development, Building Permits
Building permit applications, plan review, inspections and certificates of occupancy inside South Salt Lake city limits
220 E Morris Avenue, South Salt Lake, UT 84115
Zoning
South Salt Lake Planning & Zoning
Zoning, plats and subdivisions, and land-use applications inside South Salt Lake city limits
220 E Morris Avenue Suite 200 South Salt Lake, UT 84115
Septic permits
Salt Lake County Health Department, Water Quality Bureau
Review and permitting of new onsite wastewater (septic) systems countywide
788 East Woodoak Lane (5380 South), Murray, UT 84107
Contact details are copied from each office’s official page and were checked against it on October 24, 2026.
Off-grid gear
Going off-grid in South Salt Lake means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Does South Salt Lake, UT have zoning?
Yes. South Salt Lake adopts zoning regulations by city ordinance, and the city's Planning & Zoning division administers them under Title 17, the Land Use Ordinance17. The city publishes an interactive zoning map and a zoning map PDF, and every parcel carries its own district8.
That matters because lot size, setbacks and allowed uses vary by district, and we could not confirm the lot-size and setback standards for the R1 single-family district or any other8. Look up the parcel on the city's zoning map first, then ask Planning & Zoning about lot size, setbacks and height for that district.
Salt Lake County's Title 19 zoning covers only unincorporated land; property inside one of the county's municipalities follows municipal zoning codes9. Do not use county setback or lot-size figures for a South Salt Lake lot.
Do you need a building permit in South Salt Lake, and who issues it?
Yes, for most work. South Salt Lake requires a building permit for new construction, additions, remodels, repairs, demolitions, changes in use or occupancy, and most electrical, plumbing, mechanical and gas work210. Some minor work may be exempt, and the city asks you to call its building line to confirm before you assume a project is exempt2.
The city's own Community Development office issues the permit, not Salt Lake County or the Greater Salt Lake Municipal Services District, which serve unincorporated areas1011. Construction follows codes adopted by the city and the state of Utah12. Work started without a permit can draw a citation and a double application fee2.
Do you need an inspection or certificate of occupancy in South Salt Lake?
Every South Salt Lake building permit requires an inspection, and work finished without one must be removed or replaced so it can be inspected4. When the work is complete and meets code, the city issues a certificate of occupancy or a certificate of completion1310.
The city says it reviews a building permit application and gives feedback within 15 business days, and an application is valid for 180 days14. Fees are listed in the city's consolidated fee schedule, which we did not review for dollar amounts15.
How do septic permits work inside South Salt Lake?
Septic is a county matter, not a city one. The Salt Lake County Health Department reviews and permits new onsite wastewater systems in Salt Lake County, and no one may install, alter or replace a system without its permit31617.
Sewer usually comes first. County health rules require a building to connect to public sewer when any part of the sewer line is within 300 feet of the property line18. We could not confirm South Salt Lake's own sewer-connection rule for new homes, so ask the city's Community Development office whether sewer reaches your lot before you plan a septic system. USDA rates only about 3.8% of Salt Lake County soils as not limited for a conventional drain field, so expect a site evaluation or an engineered system wherever septic is allowed19.
Can you live in an RV or tiny home in South Salt Lake?
We could not confirm whether South Salt Lake allows RV living or tiny-home occupancy on private land, because the city's district use tables were not available to us. Do not assume either is allowed. Ask Planning & Zoning at planning@sslc.gov about the specific parcel and district7.
One related answer is confirmed: the city has allowed internal and external accessory dwelling units since 2024, but only in the R1 and RM land use districts5. An ADU predevelopment application must be processed by the planning department before a building permit can be issued5.
Building a home in South Salt Lake: the steps, in order
- Find the parcel's zoning district on the city's interactive zoning map8.
- Ask Planning & Zoning what the district allows, and whether a predevelopment or other land-use application is needed7. Plats and subdivisions also run through that division20.
- Confirm sewer and water service with the city, and call the Salt Lake County Health Department only if septic is a possibility17.
- Apply for the building permit with Community Development10. An owner building their own home is exempt from contractor licensing, but permits and inspections still apply6.
- Book an inspection for every permit, then get the certificate of occupancy or completion413.
- Any new driveway approach, sidewalk or curb work in the public right-of-way needs an engineering permit from the city21.
What stays with Salt Lake County, and what to check before you buy in South Salt Lake
Septic permits and the countywide sewer-connection rule sit with Salt Lake County Health3. Water wells are regulated by the State Engineer through the Utah Division of Water Rights, and a well needs a valid water right first22. Land outside city limits uses the county's rules instead; see the Salt Lake County page.
Salt Lake County's effective property tax rate is about 0.6%23. Before you buy, confirm the parcel's district, sewer availability and any floodplain status with the city, since we could not confirm the city's floodplain rules.
Watch-outs
- We could not confirm South Salt Lake's lot-size, setback, height or dwelling-size rules; they vary by district, so ask Planning & Zoning before you buy7.
- RV living, tiny homes, manufactured homes and short-term rentals are unconfirmed inside South Salt Lake; get an answer in writing from the city planning division for your parcel7.
- Do not rely on unincorporated Salt Lake County or Municipal Services District pages for a South Salt Lake address; the city issues its own building permits10.
Sources
- South Salt Lake city - Planning & Zoning (South Salt Lake), quoted and re-checked
- South Salt Lake city - Building Permits (South Salt Lake), quoted and re-checked
- Septic & Onsite Wastewater Systems - Waste | Salt Lake County, quoted and re-checked
- South Salt Lake city - Building Permits (South Salt Lake), quoted and re-checked
- South Salt Lake city - ADUs (South Salt Lake), quoted and re-checked
- Utah Code Title 58, Chapter 55, Construction Trades Licensing Act exemptions (Utah statewide rule), quoted and re-checked
- South Salt Lake Planning & Zoning (sslc.gov)
- South Salt Lake city - Planning & Zoning (South Salt Lake), quoted and re-checked
- Land Use & Zoning, quoted and re-checked
- South Salt Lake Community Development, Building Permits (sslc.gov)
- Building Services | Greater Salt Lake MSD, quoted and re-checked
- South Salt Lake city - Building Permits (South Salt Lake), quoted and re-checked
- South Salt Lake city - Building Permits (South Salt Lake), quoted and re-checked
- South Salt Lake city - FAQs (South Salt Lake), quoted and re-checked
- South Salt Lake city - FAQs (South Salt Lake), quoted and re-checked
- Salt Lake County Health Regulation #13: Onsite Wastewater Systems, quoted and re-checked
- Salt Lake County Health Department, Water Quality Bureau (saltlakecounty.gov)
- Salt Lake County Health Regulation #13: Onsite Wastewater Systems, quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- South Salt Lake city - Planning & Zoning (South Salt Lake), quoted and re-checked
- South Salt Lake city - FAQs (South Salt Lake), quoted and re-checked
- Water Well Drilling Information, quoted and re-checked
- Effective property tax rate: Bolthole Index county data
Written October 24, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.