King William County, Virginia requires a building permit for a new home, plus inspections and a certificate of occupancy before move-in123. Unincorporated King William County has county zoning, and projects using a private well or septic system must obtain Health Department permits before the county zoning and building applications4567.
At a glance
- Building permit
- Required before construction through the county Building Department1
- Zoning
- County-administered in unincorporated areas, with district-specific uses and dimensions48
- Septic
- Health Department permit required before county land-use and building applications96
- Owner-builder
- Allowed conditionally with the county affidavit10
- RV living
- Permanent living, sleeping or occupancy in an RV is prohibited11
- Accessory dwelling
- One per parcel in specified districts, subject to size, occupancy and permit rules12
- Private well
- Health Department construction permit required after sanitary survey approval13
Who to call
Building permits
King William County Building Department
Building permits, plan review and inspections for King William County
180 Horse Landing Road #4, King William, VA 23086
Planning & zoning
King William County Planning & Zoning (Community Development)
Zoning, land-disturbance, subdivision and parcel-boundary applications
180 Horse Landing Road #4, King William, VA 23086
Septic permits
King William County Health Department — Three Rivers Health District
Local health-department contact for King William County; ask for onsite sewage and private-well services
172 Courthouse Lane, King William Courthouse, VA 23086
Contact details are copied from each office’s official page and were checked against it on October 10, 2026.
Off-grid gear
Going off-grid in King William County means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in King William County, Virginia?
Yes. King William County requires a permit before a building or temporary structure is erected, constructed, altered, moved, converted, extended or enlarged1. The Virginia Uniform Statewide Building Code supplies the construction rules, and the county Building Department reviews plans and performs the required inspections14152. A certificate of occupancy is required before occupying permitted construction3. A homeowner may act as the builder by completing the county affidavit and satisfying its ownership and licensing conditions10. A qualifying farm building can be exempt from the state Building Code, but that exemption does not answer every county zoning, floodplain or land-use requirement16. King William County publishes a fee schedule, accepts building-permit fees online and adds a 2% state levy; confirm the project total with the Building Department17.
Who is the King William County building department, and how do you reach it?
The King William County Building Department handles new-construction plan review, code compliance and building inspections15. The office is at 180 Horse Landing Road #4, King William, VA 23086; call 804-769-4969 or email permits@kwc.gov15. Planning & Zoning is at the same address and can be reached at 804-769-4980 for zoning, land-disturbance and subdivision questions18. Both building and land-use applications have access to the county's online public portal18. The county's published sequence puts any needed well and septic permit first, followed by the Land Disturbance/Zoning Permit and then the building application7. The Building Official reviews the plans for code compliance, and the permit issues after approval and payment719.
Does King William County have zoning?
King William County applies its zoning ordinance throughout the county's unincorporated territory, with district-specific use and dimensional rules48. Incorporated municipalities may exercise separate authority, so a West Point address should not be assumed to follow the county's unincorporated-area rules20. The primary-district schedule sets minimum lot areas of 5 acres in A-C and 3 acres in R-R; R-1 ranges from 15,000 to 30,000 square feet depending on public water and sewer availability21. Front setbacks from a local or subdivision road with a right-of-way of at least 50 feet are 75 feet in A-C, 50 feet in R-R and 40 feet in R-122. Other roads, districts, recorded plats and project types can change the applicable setback23. Minimum dwelling size is set by district; in a Planned Unit Development district a detached single-story home must have at least 1,400 square feet and a two-story home 1,800 square feet, excluding attached garages, carports and porches24. Building-height limits also vary by district and use25. Ask Planning & Zoning to identify the parcel's district and the exact schedule before siting improvements18. Subdivision requires an approved, recorded plat and compliance with the ordinance26.
How do septic permits work in King William County?
Onsite sewage permitting for King William County projects runs through the Virginia Department of Health, and the county requires the Health Department well/septic permit before its land-use and building applications967. Contact the King William County Health Department at 172 Courthouse Lane, King William Courthouse, VA 23086, or 804-769-4988, and ask for onsite sewage and private-well services27. A county sewage-disposal construction permit is valid for 18 months and can be extended once for 18 months if unavoidable delays occur and the request comes before it expires28. Once the system is installed and inspected and the installer submits a completion statement, the Health Department issues an Operation Permit29. Virginia requires a written permit before an onsite sewage system is constructed, operated, expanded or modified30. During residential construction, the county requires inspection after the septic or sewer line is connected and before backfill; the inspection must precede the final inspection31. Only about 10.4% of county soils are rated without severe limits for a conventional septic drain field, so make septic feasibility an early purchase contingency rather than assuming a conventional system will fit32. A private well likewise requires a Health Department construction permit after the sanitary survey is approved13.
Can you live in an RV or tiny home on your land in King William County?
King William County prohibits using a recreational vehicle or similar equipment for permanent living, sleeping or other occupancy11. The ordinance evidence does not settle temporary camping by an owner, so ask Planning & Zoning before using an RV even temporarily on a private parcel18. The ordinance does not define "tiny home," and its occupancy rule reaches a tiny home only when the unit qualifies as a recreational vehicle or similar equipment, which cannot be lived in permanently on a residential lot33. A tiny home proposed as a dwelling must still fit the parcel's zoning and proceed through applicable building permits, inspections and the certificate-of-occupancy process4123. A county accessory dwelling is a narrower option: only one is allowed per parcel in the specified residential and agricultural districts, with limits on its form, size and occupant, and an RV cannot serve as the accessory dwelling12. Before ordering a unit, give Planning & Zoning the parcel number and describe its foundation, dimensions, utilities and intended occupancy18.
Building a home in King William County, Virginia: the steps in order
- Ask Planning & Zoning to confirm the zoning district, proposed residential use, lot size and setbacks8212218. If the project divides land, resolve the subdivision plat before designing lots26.
- Take the well/septic permit and land plat to Planning & Zoning for the Land Disturbance/Zoning Permit718.
- Submit the building application and required plans to the Building Department; owner-builders must complete the county affidavit71015.
- Obtain separate trade permits and schedule required inspections, including the septic or sewer-line inspection before backfill73431.
- Complete final health, zoning and building approvals, then obtain the certificate of occupancy before moving in35.
What should you check before buying land in King William County?
Start with buildability: confirm the district, allowed use, minimum lot area and setbacks with Planning & Zoning8212218. Make septic suitability a contract contingency because only about 10.4% of county soils are rated without severe limits for a conventional drain field32. For a private well, budget for the Health Department application, sanitary survey, construction permit and approval inspection13. Check whether the entrance touches a VDOT-maintained highway, since work in that right-of-way needs a state land-use permit36. A driveway crossing a Chesapeake Bay Resource Protection Area also faces county review and must minimize the encroachment and water-quality effects37. Development in the floodplain district must follow the county floodplain article38. If the parcel is being split, verify the approved and recorded subdivision plat26. The county's effective property-tax rate is about 0.6%, and the median bill is about $1,733 a year3940.
Watch-outs
- Do not start with the house plan alone: King William County puts the Health Department well/septic permit and county Land Disturbance/Zoning Permit before the building application7.
- Only about 10.4% of King William County soils are rated without severe limits for a conventional septic drain field, so verify a workable system before closing on rural land32.
- Permanent RV occupancy is prohibited in King William County, while temporary private-land camping and tiny-home treatment could not be confirmed; ask Planning & Zoning before placing either on a parcel1118.
- A mapped floodplain district is not a promise of flood protection; county floodplain rules apply to development there, and flooding or flood damage can still occur38.
Sources
- Building Permit Process, quoted and re-checked
- Inspections, quoted and re-checked
- Certificates of Occupancy, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- Building Permit Process, quoted and re-checked
- Building Permit Process, quoted and re-checked
- Building Permit Process, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- Division of Onsite Water and Wastewater Services, quoted and re-checked
- Residential Building Application, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- Private Well Program, quoted and re-checked
- Virginia Uniform Statewide Building Code (USBC), quoted and re-checked
- King William County Building Department (kwc.gov)
- Code of Virginia § 36-99. Provisions of Code; modifications (Virginia statewide rule), quoted and re-checked
- Building Fees, quoted and re-checked
- King William County Planning & Zoning (Community Development) (kwc.gov)
- Building Permit Process, quoted and re-checked
- § 15.2-2280. Zoning ordinances generally (Virginia statewide rule), quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, Rev. 4/13/26, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- King William County Health Department — Three Rivers Health District (vdh.virginia.gov)
- Permits To Construct A Sewage Disposal System and/or Private Well, quoted and re-checked
- Permits To Construct A Sewage Disposal System and/or Private Well, quoted and re-checked
- 12VAC5-610-240. Permits; general (Virginia statewide rule), quoted and re-checked
- Inspections, quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- King William County Zoning & Subdivision Ordinance, Rev. 4/13/26, quoted and re-checked
- Inspections, quoted and re-checked
- Inspections, quoted and re-checked
- Land use permits (Virginia statewide rule), quoted and re-checked
- King William County Zoning & Subdivision Ordinance, quoted and re-checked
- kwc.gov, quoted and re-checked
- Effective property tax rate: Bolthole Index county data
- Median property tax bill: Bolthole Index county data
Written October 10, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.