Unincorporated Bulloch County, Georgia requires building permits, including for any structure over 200 square feet, and a homeowner who is not a contractor may build their own home12. The county zoning ordinance covers all unincorporated land, while incorporated cities may apply their own rules3. Septic approval comes from the Bulloch County Health Department, or from Statesboro Water/Wastewater where municipal sewer serves the parcel4.
At a glance
- Building permit
- Required in unincorporated Bulloch County for most construction5
- Zoning
- Yes, the county ordinance covers all unincorporated land3
- Septic authority
- Bulloch County Health Department handles septic approval6
- RV living
- Not permanent habitation; utility hookups require an authorized park or temporary occupancy7
- Driveway/road permit
- County Engineer approval is required before work in a county right-of-way8
- Owner-builder
- A non-contractor may build their own home; no second home permit within 2 years of the Certificate of Occupancy2
- Minimum home size
- A detached site-built home needs at least 975 square feet of heated floor area9
- Permit threshold
- Any structure over 200 square feet (garage, pole barn, shed) needs a permit10
Who to call
Building permits
Bulloch County Building Permit/Inspection Department
Building permit issuance and inspection for unincorporated Bulloch County, including residential, commercial, manufactured home and accessory structure permits
Zoning
Bulloch County Planning and Zoning (Development Services)
Zoning, rezoning, conditional use, variances, subdivision and land-use administration for unincorporated Bulloch County
115 N Main St, Statesboro, GA 30458
Septic permits
Bulloch County Health Department (Environmental Health)
Onsite sewage (septic) system permitting and well-water testing for Bulloch County, under the Georgia Department of Public Health
1 West Altman Street, Statesboro, GA 30458
Roads & driveways
Bulloch County Public Works (Roads)
Driveway access permits, road-cut permits and the county road fee schedule for unincorporated Bulloch County
Roads & driveways
Bulloch County Engineering Department (County Engineer)
Road, drainage and driveway right-of-way engineering review for Bulloch County
Contact details are copied from each office’s official page and were checked against it on October 10, 2026.
Off-grid gear
Going off-grid in Bulloch County means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Bulloch County, Georgia?
Yes. Unincorporated Bulloch County requires building permits for new construction, additions, renovation, manufactured-home setup, swimming pools and decks over 200 square feet, and for structures over 200 square feet such as garages, pole barns, storage buildings and sheds5. Painting, flooring and cabinet work, fences under 6 feet high and retaining walls under 3 feet do not need one5. Homeowners may obtain permits5, and a non-contractor may build their own home, but cannot receive another permit to build another home within 2 years of the Certificate of Occupancy2. A pre-owned manufactured home needs a photo-based existing-conditions evaluation before a permit is issued, and the county does not allow permits for a mobile home built before June 15, 19765. The application package requires a 911 address, warranty deed or plat, site plan and wastewater approval; commercial and industrial plans also need a design-professional stamp and must satisfy current code and zoning design standards11. The stated review time is about 10 days for new homes and additions, about 5 days for manufactured homes, and as long as 3 weeks when an engineered grading plan is needed10.
Who is the Bulloch County Building Department, and how do you reach them?
The Bulloch County Building Permit/Inspection Department issues permits and conducts inspections for construction in the unincorporated county10. Call (912) 489-1356 or email inspections@bullochcounty.net the day before an inspection, between 8:00 a.m. and 5:00 p.m., with the permit number, inspection type and contact information10. Planning and Zoning handles zoning determinations, rezonings, conditional uses, variances and subdivision review at 115 N Main St, Statesboro, GA 30458, using the same phone number12. Applications and permit status are available through the Building Department's online portal10.
Does Bulloch County have zoning?
Yes. Bulloch County's Zoning Ordinance covers all land in the unincorporated county; incorporated municipalities may apply different rules, so inside a city check zoning with the city313. The official zoning map is the final authority for district boundaries, with districts including AG-5, R-80, R-40, R-25, R-15, R-8, R-2 and R-3 as well as commercial, industrial, planned-development and manufactured-home districts14. Standards change by district: AG-5 generally requires 5 acres, setbacks of 100 feet in front, 30 feet on the sides and 50 feet in the rear, and a 45-foot building-height limit151617. A detached site-built house must have at least 975 square feet of heated floor area9. Planning and Zoning should identify the parcel's mapped district before you rely on any dimensional standard14.
How do septic permits work in Bulloch County?
Bulloch County requires wastewater approval with a building application4. A parcel served by municipal sewer uses Statesboro Water/Wastewater, while a septic system goes to the Bulloch County Health Department for approval46. Georgia requires the Board of Health to approve the site and issue a construction permit before installation, followed by final inspection and written approval before backfilling or use18. Call the Health Department at (912) 764-5969 and ask for Environmental Health619. Only about 4.4% of Bulloch County soils are rated without severe limitations for a conventional drain field, so make the site evaluation an early feasibility step20. Georgia also requires a sewer connection when an available public or community system lies within 200 feet of the property line or in an abutting public right-of-way, subject to the stated exception for some failing residential systems21.
Can you live in an RV or tiny home on your land in Bulloch County?
An RV is not permanent habitable space in unincorporated Bulloch County and cannot connect to on-site water or sewer unless it is in an authorized RV park or is being used as an authorized temporary occupancy unit7. Even in an authorized RV park, a vehicle or space cannot be occupied for more than 30 days22. A tiny site-built home must satisfy the local zoning and building framework, including Bulloch County's 975-square-foot minimum heated floor area for a detached site-built house9. We could not confirm a separate county classification for tiny homes, so ask Planning and Zoning how the proposed unit will be classified. A qualifying group of manufactured homes on one parcel or contiguous commonly owned parcels is treated as a manufactured-home park and must use the Manufactured Home Park zoning district23.
Building a home in Bulloch County: the steps, in order
- Ask Planning and Zoning to confirm the parcel's official zoning district and whether the proposed use is allowed1412.
- Obtain a 911 address and prepare the warranty deed or plat and a site plan11.
- Secure wastewater approval from Statesboro Water/Wastewater or, for septic, the Bulloch County Health Department4.
- Obtain County Engineer approval before installing improvements or doing construction in a county right-of-way8.
- Submit the building-permit application and supporting documents; address Fire Marshal and flood-hazard requirements when they apply1124.
- Schedule building and soil-erosion inspections at (912) 489-1356 or inspections@bullochcounty.net the day before service is needed10.
- Ask the Building Permit/Inspection Department when a Certificate of Occupancy is required for the specific project, because we could not confirm the general trigger.
What to check before you buy land in Bulloch County
Verify the parcel's district on the official zoning map, then compare the district's lot size, setbacks, height and permitted uses with the project14151617. If the seller proposes a split, confirm subdivision review before relying on a new plat or promised access because the county regulates plats, infrastructure, access and utilities on unincorporated land25. Check road frontage and obtain County Engineer approval before work in a county right-of-way8. Ask Planning and Zoning about the flood map and applicable flood-hazard requirements because the county administers a Flood Ordinance24. Test septic feasibility early: only about 4.4% of county soils are rated without severe limits for a conventional drain field20. We could not confirm county rules for private-well permits or off-grid sanitation, so ask Environmental Health before assuming either will be approved.
Watch-outs
Sources
- Building Permits - Bulloch County, quoted and re-checked
- Permitting - Bulloch County, quoted and re-checked
- Planning & Zoning, quoted and re-checked
- Building Permit Application - Bulloch County, quoted and re-checked
- Building Permits - Bulloch County, quoted and re-checked
- Building Permit Application, quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- Appendix A – Subdivision Regulations, quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- Bulloch County Building Permit/Inspection Department (bullochcounty.net)
- Building Permit Application - Bulloch County, quoted and re-checked
- Bulloch County Planning and Zoning (Development Services) (bullochcounty.net)
- Planning and Zoning - Bulloch County, quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- Manual for On-Site Sewage Management Systems (Georgia statewide rule), quoted and re-checked
- Bulloch County Health Department (Environmental Health) (dph.georgia.gov)
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- GA DPH Onsite Sewage Manual (Georgia statewide rule), quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- The Zoning Ordinance of Bulloch County, Georgia, quoted and re-checked
- bullochcounty.net, quoted and re-checked
- bullochcounty.net, quoted and re-checked
Written October 10, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.