Anaconda-Deer Lodge County, Montana requires building permits throughout the county, and new residential work cannot start until the physical permit is issued1. Zoning works through development districts that the county's Planning Department administers, and septic permits come separately from Tri-County Environmental Health23.
At a glance
- Building permit
- Required throughout the county; obtain the physical permit before starting work1
- Zoning
- Development-district regulations apply; use the county planning map to identify the parcel's district2
- Septic
- Tri-County Environmental Health permits onsite systems; subdivision history and site conditions affect review345
- Wells
- A county well permit is required in Anaconda-Deer Lodge County6
- RV living
- Long-term occupancy on private land was not confirmed; ask the Planning Department about the parcel's district7
- Tiny homes
- Occupancy and minimum dwelling size were not confirmed; ask Planning before choosing a design7
- Owner-builder
- A state contractor-licensing exemption may apply, but county permits and inspections still apply8
Who to call
Building permits
Anaconda-Deer Lodge County Building Inspector
County building permits and help with the building process; electrical, plumbing and mechanical permits and inspections are outside this office's scope
A-DLC Courthouse, First Floor, 800 Main Street, Anaconda, MT 59711
Zoning
Anaconda-Deer Lodge County Planning Department
Development-district identification and applications for development, building and demolition permits
ADLC Courthouse, First Floor, 800 Main Street, Anaconda, MT 59711
Septic permits
Tri-County Environmental Health
Environmental-health service for Anaconda-Deer Lodge, Granite and Powell counties; county claims identify it as the onsite wastewater permitting authority
A-DLC Courthouse, Third Floor, 800 Main Street, Anaconda, MT 59711
Contact details are copied from each office’s official page and were checked against it on October 9, 2026.
Off-grid gear
Going off-grid in Deer Lodge County means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Deer Lodge County, Montana?
Yes. Anaconda-Deer Lodge County requires building permits throughout the county, and new residential construction cannot begin until the paperwork is final and the physical permit has been obtained1. The county's certified building-code program is residential-only9. Electrical, plumbing and mechanical permits and inspections belong to the Montana Department of Labor and Industry rather than the county Building Inspector10. Montana exempts an owner working on the owner's property from the construction-contractor licensing chapter in qualifying circumstances, but that exemption does not waive building, trade or inspection requirements8. The permit holder must notify the inspector when work is ready and provide access, but the complete county inspection sequence and any general certificate-of-occupancy requirement could not be confirmed; ask the Building Inspector before scheduling work1112.
Who issues Deer Lodge County building permits, and how do you reach them?
The Anaconda-Deer Lodge County Building Inspector is the local building-permit contact at 406-563-4011, in the A-DLC Courthouse, First Floor, 800 Main Street, Anaconda, MT 5971112. Planning, reached at 406-563-4010 in the same courthouse, posts the building, development and demolition applications7. A new-home application needs an Administrative Development Permit and a full plan set from a registered design professional or engineer; the departments require at least two weeks to review a complete application and plans13. Residential building fees are published, including a plan-review charge equal to 25% of the building-permit fee14. Because the local certified program is residential-only, ask the Building Inspector where to file a nonresidential project9.
Does Deer Lodge County have zoning?
Yes. Anaconda-Deer Lodge County's Development Permit System acts as zoning throughout the county through development districts, rather than one uniform set of dimensional standards1516. Use the ADLC Planning Map to identify the parcel's district, then read that district's regulations in the Development Permit System2. In the Opportunity Development District, new or expanded principal and accessory structures have a 35-foot front setback and 10-foot side and rear setbacks, subject to any superseding stream-bank or environmental standard17. The same district has a 2.5-acre minimum lot size and requires 50 feet of lot width at the building setback line18. In the East Valley Development District, new or expanded structures have a 35-foot front setback and 10-foot side and rear setbacks19. The Opportunity Development District also lists single-family dwellings, including Class A and Class B manufactured homes, at one unit per lot of record, subject to an Administrative Development Permit20. Montana law requires county zoning to allow at least one accessory dwelling unit by right on a lot with a single-family dwelling21. Those district figures do not apply countywide, and a countywide minimum dwelling size, lot coverage or building height could not be confirmed; ask Planning for the mapped district's standards7.
How do septic permits work in Deer Lodge County?
Tri-County Environmental Health requires a permit to construct, alter or repair an individual onsite wastewater system in Deer Lodge County4. Applications must document the property, site plan, nearby wells and drainfields, surface water, slopes, soils and groundwater; the fee is paid to the treasurer in the county where the property lies22. Septic application fees are $100 with a certified installer and $150 with an uncertified installer, with separate charges for some evaluations, repeat inspections and other services23. Systems installed by non-certified installers must be inspected; certified installers may self-inspect but are asked to give 24 hours' notice before burial, and an as-built drawing is due within 30 days after installation24. Septic permits stay with Tri-County Environmental Health, separate from the county building permit and from the Montana Department of Labor and Industry trade permits.410 Only about 9% of county soils are rated without severe limits for a conventional drain field, so establish feasibility before fixing the house site25. If an approved public sewer is readily available within 200 feet of the property line and the system operator approves, wastewater must connect to it unless connection is unavailable or economically impractical26.
Can you live in an RV or tiny home on your land in Deer Lodge County?
We could not confirm a countywide rule for long-term RV occupancy, temporary camping on private land or tiny-home occupancy in Deer Lodge County; ask Planning how the parcel's development district treats the proposed unit before buying land or moving it onsite7. Montana's camping limit for Fish, Wildlife & Parks sites does not answer private-land occupancy27. Property with human occupancy that is not served by municipal sewer needs wastewater facilities approved by Tri-County Environmental Health28. A tiny home may also trigger the countywide building-permit process, so take its plans and specifications to both Planning and the Building Inspector297. We also could not confirm a countywide minimum dwelling size; Planning should confirm it and the manufactured-home rule for the mapped district7.
Building a home in Deer Lodge County: the steps, in order
- Identify the development district on the Planning Map and confirm its rules with Planning2.
- Prepare the Administrative Development Permit and a full plan set from a registered design professional or engineer13.
- Resolve septic, well and subdivision-sanitation review with Tri-County Environmental Health; a county well permit is required for well drilling303132.
- Ask whether the construction site needs a driveway approach permit; when applicable, it is a prerequisite to building-application approval33.
- Obtain the physical permit before construction, then give the required notice for inspections1.
What should you check before buying land in Deer Lodge County?
Start with buildability, not the asking price. Only about 9% of Deer Lodge County soils are rated without severe limitations for a conventional septic drain field, while about 39.4% of the land has slopes of 15% or less2534. Ask Tri-County Environmental Health whether the parcel has a sanitation approval or restriction: parcels created before subdivision regulations and parcels over 20 acres receive local review, and additional testing or engineering may be needed5. Confirm the development district and allowed use with Planning, then verify legal access and ask whether the construction site requires a driveway approach permit233. We could not confirm the county's current floodplain-development process, so ask Planning before placing a home, fill or access road in a mapped hazard area7. A new well that uses more than 35 gallons per minute or 10 acre-feet per year needs a state water permit, while smaller wells may qualify for an exception that is not automatic.3536 The effective property-tax rate is about 0.8%, and the median annual bill is about $1,7063738.
Watch-outs
- Electrical, plumbing and mechanical permits and inspections are handled by the Montana Department of Labor and Industry, not the county Building Inspector12.
- No countywide RV, tiny-home, minimum-dwelling-size or setback answer was confirmed; ask Planning for the rules in the parcel's mapped development district7.
- A county well permit is required for well drilling, and new residential sites may also need septic and driveway approvals before the building application can be approved639.
Sources
- Building Permit Application, quoted and re-checked
- Planning Department, quoted and re-checked
- Septic Systems / Wells, quoted and re-checked
- Tri-County Environmental Health Onsite Wastewater Treatment Regulations, quoted and re-checked
- Sanitation in Subdivisions, quoted and re-checked
- Septic Systems / Wells, quoted and re-checked
- Anaconda-Deer Lodge County Planning Department (adlc.us)
- MCA — Construction Contractors, quoted and re-checked
- Certified City, County and Town Programs, quoted and re-checked
- Building Inspector, quoted and re-checked
- Building Permits, quoted and re-checked
- Anaconda-Deer Lodge County Building Inspector (adlc.us)
- Building Permit Application, quoted and re-checked
- Building Permit Application, quoted and re-checked
- Planning Department, quoted and re-checked
- Planning Department, quoted and re-checked
- adlc.us, quoted and re-checked
- adlc.us, quoted and re-checked
- Chapter 24 — Development Permit System, quoted and re-checked
- Opportunity Development District, quoted and re-checked
- 76-2-215. Accessory dwelling units -- regulations -- restrictions, MCA (Montana statewide rule), quoted and re-checked
- Tri-County Onsite Wastewater Treatment Regulations, quoted and re-checked
- Tri-County Onsite Wastewater Treatment Regulations, quoted and re-checked
- Tri-County Environmental Health Onsite Wastewater Treatment Regulations, quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- Building Permit Application, quoted and re-checked
- Public Use Rules and Regulations (Montana statewide rule), quoted and re-checked
- Tri-County Onsite Wastewater Treatment Regulations, quoted and re-checked
- Building Inspector, quoted and re-checked
- Building Permit Application, quoted and re-checked
- Septic Systems / Wells, quoted and re-checked
- Sanitation in Subdivisions, quoted and re-checked
- Building Permit Application, quoted and re-checked
- Share of land at 15% slope or less: Bolthole Index county data
- Exempt Well Updates and Information (Montana statewide rule), quoted and re-checked
- Exempt Well Updates and Information (Montana statewide rule), quoted and re-checked
- Effective property tax rate: Bolthole Index county data
- Median property tax bill: Bolthole Index county data
- Building Permit Application, quoted and re-checked
Written October 9, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.