Hand County, South Dakota

Building permits, zoning and septic rules in Miller, South Dakota

Building inside Miller, South Dakota, takes a city building permit, which the Miller City Council approves after the Finance Office takes the application1. Miller zones its own land under Chapter 40 of the Code of Miller2. We could not confirm who issues septic approvals inside city limits, so ask the state Department of Agriculture and Natural Resources3.

At a glance

Building permit
Required from the City of Miller; the City Council issues it4
Who takes applications
City of Miller Finance Office1
Zoning
City zoning under Chapter 40 of the Code of Miller2
House setbacks
At least 20 ft front and rear, 6 ft sides5
Permit fee
$35 for work valued $500.01 to $50,000; $50 for $50,000.01 to $100,0006
Septic
Not confirmed inside city limits; state rules come from DANR3
Electrical and plumbing
Permitted and inspected by the state, not the city7

Who to call

Building permits

City of Miller Finance Office

Building permit applications and zoning review inside Miller city limits

(605) 853-2705

120 W 2nd St Miller, SD 57362

Septic permits

South Dakota Department of Agriculture and Natural Resources

State on-site wastewater installation requirements and plan-review questions

(605) 773-4647

Contact details are copied from each office’s official page and were checked against it on October 24, 2026.

Off-grid gear

Going off-grid in Miller means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Do you need a building permit in Miller, South Dakota?

Yes. The City of Miller requires a building permit for proposed work inside city limits, and work may not begin until the Miller City Council issues it4. The application lists new construction, additions, change of use, move-on or relocation, accessory buildings of 100 square feet or more, fences and other work4.

Once issued, a permit expires unless work starts within 60 days and finishes within one year of approval4. Electrical and plumbing work is permitted and inspected separately by state inspectors, and the applicant is responsible for obtaining those permits7.

Who issues building permits in Miller, and how do you reach them?

The Finance Office at the City of Miller handles all building permit applications. The City then looks at lot lines, zoning ordinances and other pertinent factors, and the City Council makes the decision1. An application with incomplete or missing documents can be rejected or delayed1.

The city's permit form lists the City of Miller at 120 W 2nd St, Miller, SD 57362, phone (605) 853-27058. Inside Miller, do not go to the Hand County zoning counter: that office serves unincorporated Hand County, and the county's own page says its zoning ordinance applies in the unincorporated areas9. For land outside the city, see the Hand County page.

Does Miller have zoning, and what does it mean for setbacks?

Miller has its own zoning: the city's permit form names Chapter 40 of the Code of Miller as the applicable zoning law, and a variance from the zoning ordinance can be part of a complete application2. A variance carries a nonrefundable $150 fee6.

For houses, the structure must sit at least 20 feet from the front and rear lot lines and 6 feet from the side lot lines, and should line up with other houses in the block5. Accessory buildings must be at least 6 feet from the side lot line and 5 feet from the rear lot line5. We could not confirm Miller's zoning districts, minimum lot size, minimum dwelling size, or rules for RVs, tiny homes and accessory dwellings; ask the Finance Office before you buy.

What does a building permit cost in Miller?

Miller's building permit fee depends on the estimated cost of construction. It is $15 for work valued at $1.00 to $500.00, $35 for $500.01 to $50,000.00, $50 for $50,000.01 to $100,000.00, $75 for $100,000.01 to $250,000.00, $150 for $250,000.01 to $500,000.00, and $200 for $500,000.01 and up6. The same form lists a $250 administrative fee for preparing bids and contracts to correct or abate a violation6.

How do septic permits work inside Miller?

We could not confirm who issues septic approvals inside Miller city limits, or whether the city requires any. South Dakota regulates on-site wastewater systems under SDCL Chapter 34A-2, and its rules are minimum standards that local governments may tighten10. Whoever the approving office is, only a person holding an individual and small on-site wastewater system installer license may install, alter or repair a system11.

A lot connected to city water and sewer may not need a septic system at all, but we could not confirm a mandatory connection rule. Call the City of Miller Finance Office and the state Department of Agriculture and Natural Resources at (605) 773-4647 before you plan a system12.

Can you live in an RV or tiny home in Miller?

We could not confirm. Miller's zoning exists, but the ordinance text on RV occupancy, temporary camping and tiny homes was not available to us2. Manufactured and mobile homes are addressed by city ordinance, and in areas of special flood hazard they must be elevated and anchored to resist flotation, collapse or movement13. Ask the Finance Office before you move any unit onto a lot.

Building a home in Miller: the steps, in order

  1. Call the City of Miller Finance Office at (605) 853-2705 and confirm zoning for your lot8.
  2. Draw a site plan showing boundaries, setbacks and access from the public right-of-way; a survey may be required at the City Council's request5.
  3. File the building permit application and fee with the Finance Office1.
  4. Wait for the City Council's approval before any work begins4.
  5. Obtain state electrical and plumbing permits and call for inspections7.

What stays with Hand County and the state, and what to check before you buy

Hand County's zoning ordinance covers only unincorporated land, so it is the wrong office for a lot inside Miller9. If you plan a well, a water-right permit may be required, and if so it must be approved before drilling14. In flood-prone areas, permits are required for all types of development, and new or substantially improved homes must be elevated above the Base Flood Elevation15. Hand County's typical home value is about $265,85316, and its effective property tax rate is 0.9%17.

Watch-outs

  • We could not confirm septic rules inside Miller city limits; ask the City of Miller Finance Office and the state Department of Agriculture and Natural Resources3.
  • We could not confirm Miller's zoning districts, minimum lot size or rules for RVs and tiny homes; ask the Finance Office before you buy2.
  • Electrical and plumbing permits come from the state, not the city, and a city building permit does not replace them7.

Sources

  1. Hand County Multi-Jurisdictional Hazard Mitigation Plan (Miller), quoted and re-checked
  2. City of Miller Building Permit Application (Miller), quoted and re-checked
  3. On-Site Wastewater Systems in South Dakota (South Dakota statewide rule), quoted and re-checked
  4. City of Miller Building Permit Application (Miller), quoted and re-checked
  5. City of Miller Building Permit Application (Miller), quoted and re-checked
  6. City of Miller Building Permit Application (Miller), quoted and re-checked
  7. City of Miller Building Permit Application (Miller), quoted and re-checked
  8. City of Miller Finance Office (cityofmillersd.com)
  9. Hand County Zoning Ordinance, quoted and re-checked
  10. One-Stop Permitting and Regulation Guide (2025 Edition), quoted and re-checked
  11. sdlegislature.gov (Miller), quoted and re-checked
  12. South Dakota Department of Agriculture and Natural Resources (danr.sd.gov)
  13. Hand County Multi-Jurisdictional Hazard Mitigation Plan (Miller), quoted and re-checked
  14. South Dakota Water Rights — Drilling a Well (South Dakota statewide rule), quoted and re-checked
  15. National Flood Insurance Program (South Dakota statewide rule), quoted and re-checked
  16. Typical home value (Zillow): Bolthole Index county data
  17. Effective property tax rate: Bolthole Index county data

Written October 24, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Miller

Miller’s own rules

  • Building permitRequired

    Proposed construction work submitted to the City of Miller inside city limits.

    • Work may not begin until the Miller City Council issues the permit.
    • Permit work must start within 60 days and finish within one year of approval.
    • The application lists new construction, additions, change of use, move-on/relocation, accessory buildings of 100 square feet or more, fences, and other activity.

    accessory-building threshold: >= 100 square feet (Listed on the building permit application.) · start-work deadline: <= 60 days (From permit approval.) · completion deadline: <= 1 year (From permit approval.)

    “I understand that work shall not begin until the permit is issued by the Miller City Council”
  • InspectionsRequired

    City-permitted construction inside Miller city limits.

    • The applicant must call for required inspections.
    • Work must be accessible for inspection.
    • Electrical and plumbing inspections are separately administered by State inspectors.
    “I am responsible for calling for all required inspections and that work shall be accessible for inspection.”
  • Local zoningPresent (with conditions)

    Land and proposed construction inside Miller city limits.

    • The permit form identifies the applicable local zoning law as Chapter 40 of the Code of Miller.
    • A variance from the zoning ordinance may be part of a complete permit submittal.
    “current Zoning law (Chapter 40, Code of Miller) established by the City of Miller.”
  • SetbacksSpecified

    Houses and accessory buildings submitted for a Miller building permit inside city limits.

    • Houses should line up with other houses in the block.
    • The form also calls for a variance from the zoning ordinance where applicable.

    house front setback: >= 20 feet · house rear setback: >= 20 feet · house side setback: >= 6 feet · accessory-building side setback: >= 6 feet · accessory-building rear setback: >= 5 feet

    “Accessory Buildings: The structure must be at least 6 ft from side lot line and 5 feet from rear lot line. Houses: The structure must be at least 20 ft from the front and rear lot lines and 6 ft from the side lot lines. House should line up with other houses in block.”
  • Manufactured homesLimited

    Manufactured homes and mobile homes inside Miller city limits.

    • In areas of special flood hazard, manufactured homes must be elevated and anchored to resist flotation, collapse, or movement.
    “Ordinances in Miller address regulations on manufactured homes/mobile homes. In areas of special flood hazard, manufactured homes be elevated and anchored to resist flotation, collapse or movement.”
  • Building in a floodplainLimited

    Manufactured homes and mobile homes in areas of special flood hazard inside Miller city limits.

    • Manufactured homes must be elevated and anchored to resist flotation, collapse, or movement.
    “In areas of special flood hazard, manufactured homes be elevated and anchored to resist flotation, collapse or movement.”
  • Permit feesPublished (with conditions)

    Miller building-permit applications inside city limits.

    • A $150 variance fee is identified as nonrefundable.
    • The City form also lists a $250 administrative fee for preparation of bids and contracts to correct or abate a violation.

    construction value $1.00–$500.00: 15 USD (Building-permit fee.) · construction value $500.01–$50,000.00: 35 USD (Building-permit fee.) · construction value $50,000.01–$100,000.00: 50 USD (Building-permit fee.) · construction value $100,000.01–$250,000.00: 75 USD (Building-permit fee.) · construction value $250,000.01–$500,000.00: 150 USD (Building-permit fee.) · construction value $500,000.01 and up: >= 200 USD (Building-permit fee.)

    “$1.00 - $500.00 15.00 $500.01 - $50,000.00 35.00 $50,000.01 - $100,000.00 50.00 $100,000.01 - $250,000.00 75.00 $250,000.01 - $500,000.00 150.00 $500,000.01 and up 200.00”
  • Permit processPublished (with conditions)

    Building-permit processing inside Miller city limits.

    • The Finance Office handles applications.
    • The City reviews lot lines, zoning ordinances, and other pertinent factors before City Council consideration.
    • The application can be rejected or delayed when required documents are incomplete.
    • The City Council makes the permit decision.
    “The Finance Office at the City of Miller handles all building permit applications. Once a building permit application is submitted, the City looks at lot lines, zoning ordinances and other pertinent factors before being considered by the City Council. The City Council makes all decisions on building permit applications.”

Rules another office applies inside Miller

Miller does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

  • Off-grid sanitationLimited

    Construction, installation, repair, or alteration of individual and small on-site wastewater systems inside Miller city limits.

    • The work may only be done by an individual holding an individual and small on-site wastewater system installer license.
    “An individual and small on-site wastewater system may only be altered, repaired, constructed, or installed by an individual with an individual and small on-site wastewater system installer license.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Miller or Hand County directly.

  • Certificate of occupancy — Occupancy of buildings inside Miller city limits.
  • Zoning districts — Zoning districts inside Miller city limits.
  • Minimum dwelling size — Dwellings inside Miller city limits.
  • Minimum lot size — Lots inside Miller city limits.
  • Lot coverage — Lots inside Miller city limits.
14 more unanswered
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Accessory dwellings
  • Who permits septic
  • Septic permit
  • Septic inspection
  • Well permit
  • Mandatory utility hookup
  • Agricultural exemption
  • Subdividing land
  • Driveway access
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Miller publishes no rule on the point, not that none exists. Hand County’s page lists the county offices to call.