The Town of Addison, Wisconsin, in Washington County, requires a permit before anyone starts a building or mechanical system, and applications go to the Town's own Zoning office12. Addison also has its own zoning ordinance, on file with the Town Clerk3. Septic permits for the town come from Washington County, not the Town4. An owner who will live in the new home may apply without a contractor certification5.

At a glance

Building permit
Required before construction; issued through the Town of Addison12
Zoning
Town zoning ordinance, on file with the Town Clerk3
Septic
Washington County sanitary permit4
Owner-builder
Owner-occupants may apply without a Dwelling Contractor Certification5
Driveway
Separate Town driveway permit for new homes6
Inspections
Scheduled directly with JP Building Inspections, not the Town7

Who to call

Building permits

Town of Addison Zoning Office

Building permit applications, zoning questions and driveway permits inside the Town of Addison; construction-code questions and inspections go to the Town's contracted inspector

zoning@addisonwi.gov

127 First St, PO Box 481, Allenton, WI 53002

Septic permits

Washington County Natural Resources Department — Land Resources

Sanitary (septic) permits and inspections for Washington County, including the Town of Addison

(262) 335-4445

landres@washcowisco.gov

333 E. Washington Street, Suite 2300 P.O. Box 2003 West Bend, WI 53095-2003

Online permits →

Contact details are copied from each office’s official page and were checked against it on October 15, 2026.

Off-grid gear

Going off-grid in Town of Addison means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Do you need a building permit in the Town of Addison, Wisconsin?

Yes. The Town of Addison's building chapter says no owner or contractor may start any building or mechanical system before getting a valid permit from the Municipal Building Inspector1. The code lists new one- and two-family homes, agricultural buildings, decks, accessory buildings, additions, structural alterations, electrical wiring, HVAC and plumbing1.

The Town enforces Wisconsin's building code chapters, which means new homes follow the statewide Uniform Dwelling Code89. An owner who occupies, or will occupy, the home can take out the permit without a Dwelling Contractor Certification5. That does not waive the permit itself10.

Who issues building permits in the Town of Addison, and how do you reach them?

The Town of Addison Zoning office takes every building permit application, at 127 First St, PO Box 481, Allenton, WI 53002, or by email at zoning@addisonwi.gov7. Questions about submitting an application go to the zoning administrator2.

Construction-code questions go to JP Building Inspections, LLC, and inspections are scheduled with JP Building Inspections directly, not with the Town7. The application asks for plans and site-plan or survey documents2. The Town publishes a 2026 fee schedule at addisonwi.gov/feeschedule; we could not read the amounts, so ask the Zoning office for the current figures11.

Does the Town of Addison have zoning, and what does it mean for RVs and tiny homes?

Yes. The Town of Addison has its own zoning ordinance, adopted in 2016, as amended, and kept on file with the Town Clerk3. Washington County does not run general zoning, so the Town's ordinance is the one that sets the district rules for a parcel inside Addison12.

We could not confirm what the Town's ordinance says about living in an RV, tiny homes, manufactured homes, accessory dwellings or camping, because the published code page does not reproduce those provisions. Before buying, ask the Zoning office at zoning@addisonwi.gov which district the parcel is in and what that district allows7.

How do septic permits work in the Town of Addison?

Washington County, not the Town, runs the sanitary-permit process for septic systems in Addison4. The county page says installing or repairing a septic system requires the owner to get a Washington County Sanitary Permit13. Certain systems need state approval first, and a county Land Use Inspector checks the installation through a series of inspections414.

The Town's new-home application also asks for the sanitary permit13. Contact the Washington County Natural Resources Department, Land Resources, for applications and fees15. We could not confirm the rules for private wells or off-grid sanitation inside Addison; ask the same office.

Building a home in the Town of Addison: the steps, in order

  1. Ask the Town Zoning office which zoning district the parcel is in and whether the use you plan is allowed37.
  2. Get the Washington County Sanitary Permit; Wisconsin does not allow a building permit for a new dwelling on a private septic system until the sanitary permit is issued1613.
  3. Submit the building permit application, plans and site plan or survey to the Town Zoning office2.
  4. Get the separate Town driveway permit; the driveway and tracking pad must be finished before construction starts6.
  5. Call JP Building Inspections for each inspection7.
  6. Request the final inspection before moving in17.

What stays with Washington County, and what to check before you buy in Addison

Septic permits and inspections stay with Washington County4. Near water, the Town's application process says County shoreland paperwork may also be required within 1,000 feet of a water body or wetland2. Washington County also runs floodplain zoning in mapped floodplains18.

A driveway onto a County Trunk Highway needs a county access permit from the Washington County Highway Department19. Splitting a parcel is governed by the Town's Land Division Ordinance, on file with the Town Clerk20. For land outside the town, see the Washington County page. Washington County's effective property tax rate is 1.2%21.

Watch-outs

  • We could not confirm whether the Town requires a certificate of occupancy; ask the Zoning office before scheduling a move-in date1.
  • Inspections are scheduled directly with JP Building Inspections, not the Town, so call them before you cover any work7.
  • The Town's published code does not show its RV, camping or tiny-home rules, so do not assume a parcel allows living in an RV while you build; ask the Zoning office first3.

Sources

  1. Chapter 158: Building Construction - Town of Addison, WI (Town of Addison), quoted and re-checked
  2. Town of Addison - Building Resources (Town of Addison), quoted and re-checked
  3. Chapter 350: Zoning - Town of Addison, WI (Town of Addison), quoted and re-checked
  4. Septic Systems/POWTS - Washington County, WI (Town of Addison), quoted and re-checked
  5. New 1 & 2 Family Building Permit Application (Town of Addison), quoted and re-checked
  6. New 1 & 2 Family Building Permit Application (Town of Addison), quoted and re-checked
  7. Town of Addison Zoning Office (addisonwi.gov)
  8. Chapter 158: Building Construction - Town of Addison, WI (Town of Addison), quoted and re-checked
  9. One- & Two-Family (Uniform Dwelling Code) (Wisconsin statewide rule), quoted and re-checked
  10. Instructions for Submitting a UDC Permit Application, quoted and re-checked
  11. Town of Addison Fee Schedule (Town of Addison), quoted and re-checked
  12. County Land Information Plan 2024, quoted and re-checked
  13. Septic Systems/POWTS - Washington County, WI (Town of Addison), quoted and re-checked
  14. Septic Systems/POWTS - Washington County, WI (Town of Addison), quoted and re-checked
  15. Washington County Natural Resources Department — Land Resources (permitapp.washcowisco.gov)
  16. Wisconsin’s Uniform Dwelling Code (Wisconsin statewide rule), quoted and re-checked
  17. Wisconsin’s Uniform Dwelling Code (Wisconsin statewide rule), quoted and re-checked
  18. Permits, Applications, and Grants, quoted and re-checked
  19. Permits, quoted and re-checked
  20. Chapter 240: Land Division - Town of Addison, WI (Town of Addison), quoted and re-checked
  21. Effective property tax rate: Bolthole Index county data

Written October 15, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Town of Addison

Town of Addison’s own rules

  • Building permitRequired

    Construction of buildings or mechanical systems inside Addison town.

    • The code lists new one- and two-family and commercial buildings, agricultural buildings, decks, accessory buildings, additions, structural alterations, major equipment, electrical wiring, HVAC, plumbing, and new or rewired electrical service.
    • Major building equipment requires a permit except as noted below in the ordinance.
    “No owner or contractor may commence construction of any building or mechanical system prior to obtaining a valid permit from the Municipal Building Inspector.”
  • Owner-builder exemptionConditional

    An owner-occupant applying for an Addison construction or erosion-control permit.

    • The applicant must be or become an owner occupant of the dwelling.
    • The form states the owner may apply without a Dwelling Contractor Certification and must read the cautionary statement regarding contractor responsibility on the second page.
    “I vouch that I am or will be an owner occupant of this dwelling for which I am applying for an erosion control or construction permit without a Dwelling Contractor Certification and have read the cautionary statement regarding contractor responsibility on the second page of this form.”
  • Building code adoptedAdopted (with conditions)

    Building construction inside Addison town.

    • The Town adopts the listed Wisconsin Administrative Code chapters and subsequent revisions; enforcement is by the Building Inspector.
    “The following chapters of the Wisconsin Administrative Code, as well as all subsequent revisions, are adopted by the municipality and shall be enforced by the Building Inspector:”
  • Local zoningPresent

    Land inside Addison town.

    • The zoning chapter states that the adopted zoning ordinance is on file at the Town Clerk's office.
    “The Zoning Ordinance for the Town of Addison, adopted 3/31/2016, as amended, is on file at the office of the Town Clerk.”
  • Who permits septicCounty (with conditions)

    Septic-system installation and repair inside Addison town; Washington County administers the sanitary-permit process.

    • Certain POWTS require state approval before the County sanitary permit.
    • A Washington County Land Use Inspector performs inspections for compliance with state codes.
    “Activities relating to the installation or repair of septic systems requires the owner of the property to obtain a Washington County Sanitary Permit.”
  • Septic permitRequired

    Installation or repair of septic systems inside Addison town.

    • The County page says state approval is needed for certain POWTS before the County sanitary permit.
    • The Town's new-home application also requires a sanitary permit.
    “Activities relating to the installation or repair of septic systems requires the owner of the property to obtain a Washington County Sanitary Permit.”
  • Septic inspectionRequired

    POWTS installed or repaired inside Addison town.

    • Inspections are conducted by a Washington County Land Use Inspector for compliance with state codes.
    • The source describes a series of inspections but does not provide a complete inspection schedule.
    “A Washington County Land Use Inspector will ensure that the POWTS is installed in compliance with state codes through a series of inspections.”
  • Subdividing landRegulated (with conditions)

    Land division and subdivision inside Addison town.

    • The Town's adopted Land Division Ordinance is on file at the Town Clerk's office; the accessible page does not reproduce its application thresholds or exemptions.
    “The Land Division Ordinance for the Town of Addison, adopted 3-31-2016, as amended, is on file at the office of the Town Clerk.”
  • Driveway accessRequired

    New one- and two-family construction inside Addison town.

    • A separate driveway permit is obtained from the Town of Addison.
    • The driveway with tracking pad must be completed before construction starts.
    • The application also requires the driveway location to be shown on the site plan.
    “Separate permit obtained from Town of Addison. Driveway with tracking pad must be completed prior tot start of construction.”
  • Permit feesPublished (with conditions)

    Town permit fees for work inside Addison town.

    • The official fee page identifies an updated 2026 fee schedule, but the fee amounts were not exposed in the accessible page text.
    “Town of Addison Updated Fee Schedule 2026”
  • Permit processPublished (with conditions)

    Building-permit applications inside Addison town.

    • Applications are submitted to the Town Zoning office or electronically to zoning@addisonwi.gov.
    • Construction-code questions go to JP Building Inspections, LLC; inspection scheduling goes directly to JP Building Inspections, not the Town.
    • The application requires plans and site-plan/survey documents; additional County shoreland paperwork may be required within 1,000 feet of a water body or wetland.
    “All building permit applications are submitted to the Town of Addison Zoning office at 127 First St, Po Box 481, Allenton, WI 53002.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Town of Addison or Washington County directly.

  • Certificate of occupancy — Certificate-of-occupancy requirements inside Addison town.
  • Minimum dwelling size — Residential dwellings inside Addison town.
  • Minimum lot size — Residential lots inside Addison town.
  • Setbacks — Principal residential buildings inside Addison town.
  • Lot coverage — Residential lots inside Addison town.
12 more unanswered
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Off-grid sanitation
  • Well permit
  • Mandatory utility hookup
  • Agricultural exemption
  • Building in a floodplain
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Town of Addison publishes no rule on the point, not that none exists. Washington County’s page lists the county offices to call.

← All of Washington County: county rules, score and offices