Unincorporated Butler County, Nebraska has no countywide zoning or confirmed residential building-permit program, but the county FAQ describes a plan-submission process that buyers should ask about before building123. Nebraska's state building code applies by default where no qualifying local code was adopted, and the state administers onsite wastewater systems45. Proposed zoning and a temporary development moratorium may also affect current plans67.

At a glance

Building permit
No county residential permit program is in place, but the county FAQ describes a plan-submission process; the state building code still applies by default234
Zoning
No countywide zoning, minimum dwelling size or minimum lot size is in force in unincorporated areas; proposed rural districts are not confirmed as adopted1896
Septic
The Nebraska Onsite Wastewater Program administers systems statewide; most typical systems use Authorization by Rule and all changed systems must be registered510
Owner-builder
Doing your own construction work exempts you from Nebraska's Contractor Registration Act, but not from any applicable building or septic permit1112
Farm buildings
Construction on a farm or for farm purposes is exempt from the state building code, and farm buildings on a 20+ acre farmstead earning $1,000+ a year can be exempt from county zoning too1314
Manufactured homes
If Butler County adopts zoning, state law would let the county board require a 900-square-foot minimum and site-built-style standards for manufactured homes15
Driveway access
A driveway connecting to a state highway needs a Nebraska Department of Transportation permit16

Who to call

Also useful

Butler County Clerk's Office

General county point of contact; serves as secretary to the County Board of Supervisors and the Planning Commission. Butler County has no separate building or zoning department, so this is the office to call about a building-permit application, the comprehensive-plan process, or the current development moratorium

402-367-7430

clerk@butlercountyne.gov

451 N. 5th Street, David City, NE 68632

Septic permits

Nebraska Department of Environment and Energy, Onsite Wastewater Program

Administers Nebraska's statewide onsite wastewater program (Title 124) covering septic systems, holding tanks and lagoons for Butler County; there is no county septic office

(402) 471-4285

dwee.onsite@nebraska.gov

245 Fallbrook Blvd. Suite 100, Lincoln, NE 68521

Online permits →

Contact details are copied from each office’s official page and were checked against it on October 9, 2026.

Off-grid gear

Going off-grid in Butler County means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Do you need a building permit in Butler County, Nebraska?

Butler County appears to have no residential building-permit program in place for unincorporated land2. Nebraska's state building code nevertheless applies by default where a county has not adopted a qualifying local code after a state-code update4. Construction on a farm or for farm purposes is outside that default state-code rule13. Butler County's FAQ separately says a building-permit application needs two identical plan sets containing a plot plan plus footing, wall, roof and floor details3. The FAQ does not identify the reviewer or explain which projects need that packet, so give the County Clerk the property's legal description and address and ask what applies17.

Who handles building permits in Butler County, and how do you reach them?

Butler County has no separate building or zoning department, so the County Clerk's Office is the practical front door for a building-permit question17. Reach the Clerk's Office at 451 N. 5th Street, David City, NE 68632, phone 402-367-7430, or clerk@butlercountyne.gov17. The County Clerk serves as secretary to both the County Board of Supervisors and the Planning Commission, making that office the right place to ask whether the FAQ plan packet, proposed zoning or temporary moratorium affects a parcel17. Bring the legal description, site address and intended use because the county FAQ does not establish the full permit process or which projects require its plan packet3. Farm-purpose construction is excluded from the default state building-code provision, but that exception does not erase separate septic, access or floodplain requirements13.

Does Butler County have zoning?

Butler County has no countywide zoning ordinance in force for unincorporated land1. Unincorporated Butler County therefore has no county zoning setbacks, lot-coverage limits or building-height limit, and no county zoning-based minimum dwelling size or minimum lot size89, although municipal zoning and separate floodplain, septic, roadway and state building rules can still apply181920. The Planning Commission has published proposed rural zoning districts and a proposed classification map, but publication does not mean they have been enacted6. The County Board approved Resolution 2026-07 on March 16, 2026, a temporary development moratorium connected with the planning process, and the available material does not establish its full duration7. Planning Commission minutes from September 2026 still describe the zoning regulations as not yet adopted21. Cities such as David City adopt their own zoning, which does not reach unincorporated land7. Ask the County Clerk whether the moratorium or a newer zoning action affects the parcel before relying on today's absence of countywide zoning17.

How do septic permits work in Butler County?

The Nebraska Onsite Wastewater Program administers septic systems, holding tanks, private lagoons and other onsite systems in Butler County5. Most systems can be constructed under Authorization by Rule without a site-specific state construction permit, but a system that is built, reconstructed, altered or otherwise changed must be registered; unusual size, non-domestic waste or difficult siting can trigger site-specific review and permits10. A Butler County dwelling that generates wastewater must connect to a public sewer or use an onsite system that complies with state rules, so living off grid does not create a sanitation exemption22. Only 16.7% of Butler County soils are rated without severe limitations for a conventional drain field, making soil and site evaluation an early purchase check23. If a planned development includes an onsite-system lot smaller than three acres, the owner must submit it for subdivision review before construction24.

Can you live in an RV or tiny home on your land in Butler County?

We could not confirm that long-term RV living or temporary camping is allowed on private land in Butler County; ask the County Clerk about the parcel and current moratorium before buying17. Nebraska's public-property camping rule covers highways, roadside areas and parks, not occupancy on private land, so it does not answer the private-parcel question25. A tiny house may be regulated as a manufactured home, modular unit or recreational vehicle26. A tiny house on a single wheeled chassis that is designed for seasonal or temporary living quarters, stays within 430 square feet and passes Nebraska Public Service Commission plan review is treated as a park trailer and receives a Nebraska Recreational Vehicle label, which is a vehicle classification rather than a permission to live on a particular parcel27. Butler County's lack of countywide zoning removes county zoning barriers, not wastewater obligations: any dwelling that generates wastewater must use a compliant onsite system or connect to sewer122.

Building a home in Butler County: the steps, in order

  1. Call the Butler County Clerk's Office at 402-367-7430 with the legal description, address and intended use; the county appears to have no residential permit program, but its FAQ describes a building-permit plan submission1723.
  2. If you are building for a farm purpose, confirm that the state building-code exception applies13.
  3. For non-farm construction, design to the state building code that applies by default where no qualifying local code was adopted4.
  4. Register the onsite wastewater system and ask the Nebraska Onsite Wastewater Program whether it qualifies for Authorization by Rule or needs site-specific permits2410.
  5. Check the soils before designing a drain field; only 16.7% of Butler County soils are rated without severe limits for a conventional system23.
  6. Obtain a state permit for a new, relocated or altered driveway connecting to a state highway16.
  7. Obtain a floodplain development permit before development in a mapped floodplain28.
  8. Obtain County Board approval before subdividing or platting unincorporated property into lots, streets or other portions29.
  9. Ask the County Clerk whether the temporary development moratorium affects the parcel before finalizing plans177.

What to check before you buy land in Butler County

Butler County is mostly gentle, open ground: 93.7% of the land has slopes of 15% or less, while 5.7% is wooded3031. Farmland averages about $6,462 per acre32. Severe drought has occurred in about 17.6% of years on record, and average precipitation is 29.6 inches a year, so confirm the parcel's water source rather than assuming a domestic well will meet the project3334. The nearest city of 100,000 or more people is about 37 miles from the county center35. A typical home value is about $248,755; the median property-tax bill is about $1,941 a year at an effective rate of 1.2%, and typical annual homeowners insurance is about $2,20936373839. Before closing, check soils, floodplain, legal access, wastewater, subdivision status, municipal jurisdiction and the temporary development moratorium23297.

Watch-outs

  • Butler County appears to have no residential permit program, but its FAQ describes a building-permit plan packet; call the County Clerk with the address and legal description before assuming no submission is needed2317.
  • Nebraska's camping statute governs public highways, roadside areas and parks, not private land — it isn't a yes-or-no answer for RV living on your own Butler County parcel25.
  • Butler County's proposed rural zoning districts are not confirmed as adopted, while the temporary development moratorium may still affect a parcel; ask the County Clerk for the current status6717.

Sources

  1. Request for Proposals for Professional Services: Comprehensive Plan Development, quoted and re-checked
  2. Butler County Planning Commission (2026 county census)
  3. butlercountyne.gov, quoted and re-checked
  4. Nebraska Revised Statute 71-6403, quoted and re-checked
  5. Onsite Wastewater Program, quoted and re-checked
  6. Planning Commission, quoted and re-checked
  7. Request for Proposals for Professional Services: Comprehensive Plan Development, quoted and re-checked
  8. NOTICE TO BIDDERS — Comprehensive Plan Development, quoted and re-checked
  9. NOTICE TO BIDDERS — Comprehensive Plan Development, quoted and re-checked
  10. Onsite Wastewater Treatment Facilities Program Overview, quoted and re-checked
  11. Nebraska Revised Statute 48-2104 — Registration required (2026 county census)
  12. Nebraska Revised Statute 48-2104 — Registration required (Nebraska statewide rule), quoted and re-checked
  13. nebraskalegislature.gov, quoted and re-checked
  14. nebraskalegislature.gov (Nebraska statewide rule), quoted and re-checked
  15. Nebraska Revised Statute 23-114 (Nebraska statewide rule), quoted and re-checked
  16. Title 410, Chapter 2 - Driveway and Approach Road Permits, quoted and re-checked
  17. Butler County Clerk's Office (butlercountyne.gov)
  18. Butler County Planning Commission Minutes – February 11, 2026, quoted and re-checked
  19. Request for Proposals for Professional Services – Comprehensive Plan Development, quoted and re-checked
  20. Request for Proposals for Professional Services – Comprehensive Plan Development, quoted and re-checked
  21. Butler County Board of Supervisors Minutes, March 16, 2026, quoted and re-checked
  22. Onsite Wastewater Program, quoted and re-checked
  23. Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
  24. Nebraska Department of Environment and Energy, Onsite Wastewater Program (dwee.nebraska.gov)
  25. Nebraska Revised Statute 39-312 — Camping; permitted; where; violation; penalty (Nebraska statewide rule), quoted and re-checked
  26. Housing and Recreational Vehicle (Nebraska statewide rule), quoted and re-checked
  27. Nebraska Tiny House Regulation, quoted and re-checked
  28. Floodplain Management Q&A: Permits (Nebraska statewide rule), quoted and re-checked
  29. nebraskalegislature.gov, quoted and re-checked
  30. Share of land at 15% slope or less: Bolthole Index county data
  31. Wooded share of land: Bolthole Index county data
  32. Farmland value per acre (USDA census): Bolthole Index county data
  33. Share of years in severe drought: Bolthole Index county data
  34. Annual precipitation: Bolthole Index county data
  35. Straight-line distance from the county center to the nearest city of 100,000+ people: Bolthole Index county data
  36. Typical home value (Zillow): Bolthole Index county data
  37. Median property tax bill: Bolthole Index county data
  38. Effective property tax rate: Bolthole Index county data
  39. Typical home insurance premium: Bolthole Index county data

Written October 9, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Found land here? Start a Property Hunt →

Compared with neighboring counties

Unlike all 6 of its neighbors, Butler County requires no county building permit for a home.

RuleButler CountyPolk CountySeward CountySaunders CountyColfax CountyLancaster CountyYork County
Building permitNot requiredRequiredRequiredRequiredRequiredLimitedRequired
County zoningNoYesYesYesYesYesYes
Septic permitsNE Dept. of Env. & EnergyNDEENDEENE Dept. of Env. & EnergyNE Dept. of WaterNDEENDEE

County locator

Butler County in Nebraska

44
County map
Butler County highlighted among the Nebraska counties · colored by Index score

How Butler County scores

Seclusion42100% ev.
Self-Sufficiency2199% ev.
Admin Boringness80100% ev.
Durability38100% ev.
Property Autonomy53100% ev.
Carry Cost61100% ev.

Evidence strength: 100%. This reports direct-source completeness and fallback use; it is separate from the score and is not a confidence interval. How it works →

$249kTypical home
1.2%Property tax
$6,462Land / acre
29.6"Annual rain
17.6% of yrsSevere drought
13 / yr (+11)Mid-century 100°F days
20.6 daysMid-century dry spell
1.83" (+2.8%)Mid-century 1-day rain
1.6×Wildfire change factor
100%Forward climate coverage
$2,209Home insurance / yr
3.5% / yrInsurance growth
4.25%Nonrenewal rate
county median (2+ published ZIPs)Insurance basis
29,784People within 30 min
1,845,725People within 2 hr
16,065Radius comparison (15 mi)
14.5People / sq mi
0.2%Federal land
93.7%Land at 15% slope or less
16.7%Soils rated "not limited" for septic (strict USDA rating)
62,236 acWorkable land screen
5.7%Wooded land
12.1 tonsBiomass / forest ac
50.4°FAvg temp

Scout Butler County

Camp here before you commitBook a few nights nearby on Hipcamp →Already own land here?Earn money hosting campers — get $100 when you become a Hipcamp host →

Some links are affiliate or referral links — we may earn a commission, at no cost to you.

Property hunt

Find land. Bring the promising ones back.

Search live inventory elsewhere, then cost and vet each candidate here. No copied listings, account, or paid data feed.

Each button opens a current land search for Butler County. Listing sites control their own results and filters.

Analyze a property
Add setup-cost allowances

Use rough quotes or placeholders. Blank fields count as $0.

Working estimate

—land + entered setup costs
Asking $ / acre
—
Setup allowance
—
All-in $ / acre
—

A planning estimate, not a valuation or contractor quote. The USDA benchmark includes farm land and buildings; it is context, not a parcel comp.

Before an offer

Parcel due diligence

0/8 checked

Saved properties and checklist progress stay on this device. Bolthole Index does not receive them.

Cities and towns in Butler County

Inside a city, town or township here, that government usually sets zoning and may issue its own building permits; the county’s rules above cover land outside them.

Village of Abie · Alexis Township · Village of Bellwood · Bone Creek Township · Village of Brainard · Village of Bruno · Center Township · David City · Village of Dwight · Franklin Township · Village of Garrison · Linwood Township · Village of Linwood · Oak Creek Township · Village of Octavia · Olive Township · Platte Township · Plum Creek Township · Read Township · Reading Township · Richardson Township · Village of Rising City · Savannah Township · Skull Creek Township · Summit Township · Village of Surprise · Ulysses Township · Village of Ulysses · Union Township

Answers from the rulebook for Butler County

What the ordinances and state agencies actually say — one answer per question, each quoted from the official source and independently re-checked.

Butler County rules

  • County-wide zoningAbsent

    County zoning regulations in Butler County, including unincorporated areas, as documented in the county's 2025 planning RFP and 2026 proposed-zoning materials.

    • The county's 2025 RFP states that Butler County had no zoning regulations and contemplated developing regulations only if the County decided to proceed.
    • The county published a September 2026 public hearing for the comprehensive plan and a document titled Proposed Butler County, Nebraska, Rural Community Zoning Districts; those materials do not establish adoption of final zoning regulations.
    • Municipal and village zoning, if any, is outside this countywide unincorporated-area claim.
    “Butler County is one of the last few remaining counties in the State of Nebraska with no zoning regulations.”
  • Local zoningVaries (with conditions)

    Countywide aggregate of land-use regulation in Butler County, including unincorporated county areas and incorporated municipalities; the county itself had no general zoning regulations, while municipal rules and temporary county development moratoria may apply.

    • The official county RFP states that Butler County had no zoning regulations as of the 2025 procurement.
    • The Planning Commission’s February 25, 2026 minutes state that the County lacked existing zoning regulations while adopting a resolution concerning temporary moratoria.
    • The County Board approved Resolution 2026-07 on March 16, 2026, mirroring the Planning Commission resolution but removing the exclusion for projects under construction; the full operative duration and text of the moratorium were not established in the opened source.
    • This is an aggregate claim and does not assert that the county administers municipal zoning ordinances.
    “Zoning Ordinance - Ordinance No. 1504 - Adopted by the City of David City January 22, 2025”
  • Zoning districtsPublished (with conditions)

    Proposed county zoning districts and proposed zoning classification map for Butler County, Nebraska; this claim does not establish that the proposal has been enacted.

    • The official page labels the materials 'Butler County Proposed Zoning Districts' and 'Butler County Proposed Zoning Classification Map'.
    • The materials are presented through the Planning Commission's comprehensive-plan process.
    • Because the source says proposed, the publication does not prove currently effective or adopted zoning districts.
    “Butler County Proposed Zoning Districts Butler County Proposed Zoning Classification Map”
  • Minimum dwelling sizeNone

    County zoning-based minimum dwelling size in unincorporated Butler County, Nebraska.

    • This absence claim is limited to county zoning-based dimensional regulation.
    • Municipal, township, state building-code, septic, floodplain, subdivision, and health requirements may still apply.
    • The September 16, 2026 minutes state that zoning regulations had not yet been adopted; the source does not provide a county minimum dwelling-size rule or effective date.
    “Reiter stated that the answer would depend on the zoning regulations that had not yet been adopted.”
    One more reviewed finding on this topic
    • None — County-level zoning minimum dwelling-size requirements for residential dwellings in unincorporated Butler County.
      “Butler County is one of the last few remaining counties in the State of Nebraska with no zoning regulations.”
  • Minimum lot sizeNone

    County zoning-based minimum lot size in unincorporated Butler County, Nebraska.

    • This absence claim is limited to county zoning-based dimensional regulation.
    • Municipal, township, state, septic, floodplain, subdivision, and health requirements may still apply.
    • The September 16, 2026 minutes state that zoning regulations had not yet been adopted; the source does not provide a county minimum-lot-size rule or effective date.
    “Reiter stated that the answer would depend on the zoning regulations that had not yet been adopted.”
    One more reviewed finding on this topic
    • None — County-level zoning minimum-lot-size requirements for residential lots in unincorporated Butler County.
      “Butler County is one of the last few remaining counties in the State of Nebraska with no zoning regulations.”
  • SetbacksNone

    County zoning setbacks in unincorporated Butler County.

    • The county FAQ says setbacks differ by zoning district, but the county's official planning materials state that county zoning districts are proposed and official Planning Commission minutes state that the county does not have zoning.
    • Municipal zoning, state building requirements, roadway setbacks, floodplain requirements, septic requirements, and other applicable regulations may still apply.
    “Butler County has a large and varied number of activities going on because the county does not have zoning.”
  • Lot coverageNone

    County zoning lot-coverage regulation in unincorporated Butler County.

    • The official county materials state that Butler County does not have zoning regulations; the county planning page identifies zoning districts as proposed.
    • Municipal zoning, state building requirements, floodplain requirements, septic requirements, and other applicable regulations may still apply.
    “Butler County has a large and varied number of activities going on because the county does not have zoning.”
  • Building heightNone

    County zoning building-height regulation in unincorporated Butler County.

    • The official county materials state that Butler County does not have zoning regulations; the county planning page identifies zoning districts as proposed.
    • Municipal zoning, state building requirements, airport hazard rules, floodplain requirements, and other applicable regulations may still apply.
    “Butler County is one of the last few remaining counties in the State of Nebraska with no zoning regulations.”
  • Permit processPartial

    Building permit applications in Butler County, Nebraska; the county FAQ provides a document-submission requirement but does not establish the complete process.

    • The official FAQ states that two identical sets of plans are required at application.
    • The stated plan package includes a plot plan, footing detail, wall detail, roof detail, and floor plan.
    • The page does not establish all review, approval, inspection, or issuance steps.

    identical plan sets: 2 sets

    “What is required for a building permit? Need two (2) identical sets of plans at the time of application, including a plot plan, footing detail, wall detail, roof detail and floor plan.”
  • Building permitNot required

    The county has no building department and no adopted zoning, and its Planning Commission is only now developing a comprehensive plan, so no county residential building permit program is in place. State overlay (NE): the state building code (IRC 2018) applies by default in counties without local codes (Neb. Rev. Stat. 71-6404) as an unenforced compliance duty — construction on a farm or for farm purposes is exempt (71-6406(1)(b)); statewide electrical wiring permits and state inspection apply (State Electrical Act).

    Butler County Planning Commission ↗Scouted from the county site, not yet independently re-checked

Nebraska rules that apply here

  • Owner-builder exemptionAvailable

    A person performing work or having work performed on the person's own property under Nebraska's Contractor Registration Act.

    • The exemption means the person is not a contractor for purposes of the Contractor Registration Act.
    • The exemption applies to work on the person's own property.
    • The statute separately states that a person earning less than five thousand dollars annually for construction services is also not a contractor for purposes of the Act.
    • The exemption does not exempt a contractor from withholding requirements under the Nebraska Revenue Act of 1967.
    • This is a contractor-registration exemption and does not establish exemption from applicable building permits, inspections, building codes, electrical requirements, or other local or state approvals.

    annual construction-services earnings threshold: < 5000 USD (Separate statutory basis for not being a contractor under the Act; the own-property exemption has no stated dollar threshold.)

    “Any person who performs work or has work performed on his or her own property or any person who earns less than five thousand dollars annually for construction services is not a contractor for purposes of the Contractor Registration Act.”
  • Building code adoptedAdopted (with conditions)

    Nebraska's state building code, including state-owned or state-agency buildings and local jurisdictions as specified by Nebraska law.

    • The adopted code consists of the 2018 International Building Code with stated exceptions, the 2018 International Residential Code with stated exceptions, the 2018 International Existing Building Code with a stated exception, the 2018 Uniform Plumbing Code, and minimum radon-resistant construction standards.
    • The state building code applies to all buildings and structures owned by the state or a state agency.
    • It applies in a county, city, or village that elects to adopt it as its local code.
    • It also applies in a county, city, or village that has not adopted an authorized local code within two years after an update to the state building code.
    • The default state-code rule does not apply to construction on a farm or for farm purposes.
    • A local jurisdiction may instead adopt a code that conforms generally with the state building code, subject to the requirements and exceptions in section 71-6406.

    International Building Code edition: 2018 (Except section 101.4.3 and chapter 29; section 305.2.3 applies to a facility having twelve or fewer children; section 310.4.1 applies to a care facility for twelve or fewer persons.) · International Residential Code edition: 2018 (Except section R313 and chapters 25 through 33.) · International Existing Building Code edition: 2018 (Except section 809.) · Uniform Plumbing Code edition: 2018 · local-code adoption deadline after state-code update: 2 years (If no authorized local code is adopted, the state building code applies, except to construction on a farm or for farm purposes.)

    “(1) There is hereby created the state building code. The Legislature hereby adopts by reference:”
    2 more reviewed findings on this topic
    • Adopted (with conditions) — The Nebraska state building code as the statewide building and construction standard, including application in Butler County when the county, city, or village has not adopted a qualifying local code within two years after a state-code update.
      “If a county [...] does not adopt a code [...] within two years after an update [...] the state building code shall apply [...] except [...] farm purposes.”
    • Adopted (with conditions) — Nebraska's state building code as it applies in Butler County when the statutory applicability conditions are met.
      “There is hereby created the state building code. The Legislature hereby adopts by reference:”
  • Camping on your landLimited

    Temporary camping on state or county public highways, roadside areas, parks, and other property acquired for highway or roadside park purposes in Nebraska.

    • Camping is unlawful except at places designated as campsites by the Department of Transportation, the county, or another governmental entity owning or controlling the property.
    • The statute excludes certain lands transferred or leased to the Game and Parks Commission and other lands controlled by the Game and Parks Commission or a natural resources district, which are governed under separate statutes.
    • Camping includes temporary lodging out of doors in a sleeping bag, tent, trailer, station wagon, pickup camper, camper-bus, or other vehicle.
    • Violation is a Class V misdemeanor and may require reimbursement for campsite damage.

    penalty: Class V misdemeanor

    “It shall be unlawful to camp on any state or county public highway, roadside area, park, [...] except at such places as are designated campsites”
  • Tiny homesLimited

    Tiny houses produced or sold in Nebraska and classified as manufactured homes, modular housing units, or recreational vehicles, including park model recreational vehicles.

    • The Nebraska Public Service Commission states that tiny houses can be built as either a manufactured home, modular housing unit, or recreational vehicle.
    • For a park model recreational vehicle under current Nebraska law, the unit must be designed and marketed as temporary living quarters for recreational, camping, travel, or seasonal use; must not be permanently affixed to real property for use as a permanent dwelling; must be built on a single chassis mounted on wheels; must have a gross trailer area not exceeding 400 square feet in the setup mode; and must be certified by the manufacturer as complying with ANSI A119.5, 2025 edition.
    • LB1147 enacted the 400-square-foot park-model limit and specified the 2020 ANSI A119.5 edition; its emergency clause states that the act takes effect when passed and approved according to law.
    • State classification or construction compliance does not establish unrestricted land-use occupancy. County zoning resolutions may regulate the location, size, and uses of structures including house trailers and automobile trailers, and may regulate uses of buildings and land in unincorporated areas.
    • County zoning powers do not apply within incorporated cities or villages, or areas where a city or village has been granted and is exercising zoning jurisdiction. Local zoning, building, utility, health, and other requirements may therefore impose additional conditions.

    park model gross trailer area: <= 400 square feet (Measured in the setup mode.) · park model chassis: single chassis mounted on wheels · park model permanent-affixation: false (The unit must not be permanently affixed to real property for use as a permanent dwelling.)

    “(16) Park model recreational vehicle means a vehicular unit which meets the following criteria: (a) Is designed and marketed as temporary living quarters for recreational, camping, travel, or seasonal use; (b) Is not permanently affixed to real property for use as a permanent dwelling; (c) Is built on a single chassis mounted on wheels with a gross trailer area not exceeding four hundred square feet in the set up mode; and (d) Is certified by the manufacturer as complying with the ANSI A119.5 Park Model Recreational Vehicle Standard of the American National Standards Institute, 2025 edition;”
    One more reviewed finding on this topic
    • Limited — Tiny houses in Nebraska that are classified as park trailers and used as seasonal or temporary living quarters; this state classification does not establish permission to occupy a particular Butler County parcel.
      “If the tiny house meets the four requirements above, along with the requirements of ANSI A119.5, and complies with Commission plan review and inspection requirements, the tiny house would be considered a park trailer and be issued a Nebraska Recreational Vehicle label to affix to the structure.”
  • Who permits septicMixed (with conditions)

    Onsite wastewater treatment systems statewide in Nebraska, including septic systems, holding tanks, lagoons, mound systems, and other decentralized systems.

    • The Nebraska Onsite Wastewater Program administers statewide Title 124 requirements.
    • Any local city or county requirements are separate from and in addition to statewide Title 124 requirements.
    “Any local requirements (city, county) are separate from and in addition to the requirements found in Title 124 that apply statewide.”
    One more reviewed finding on this topic
    • State — Onsite wastewater systems in Butler County, including septic systems, holding tanks, private lagoons, and other decentralized systems.
      “The Nebraska Onsite Wastewater Program administers regulations meant to protect surface water and groundwater as well as public health and welfare through the use of standardized design requirements, the certification of onsite professionals, the review of plans for subdivision development and the permitting of systems that because of large size, handling of non-domestic wastes, or siting issues require a site specific evaluation.”
  • Septic permitLimited

    Onsite wastewater systems in Butler County, Nebraska.

    • Typical systems may proceed under the statewide authorization mechanism without a site-specific construction or operating permit when the applicable authorization requirements are met.
    • Systems involving large size, non-domestic wastes, or siting issues require site-specific evaluation and permitting.
    • When a permit application is required, a construction permit is required before construction and an operating permit is required before wastewater discharge or use.
    • Any onsite wastewater system that is constructed, reconstructed, altered, modified, or otherwise changed must be registered with the Department.
    “Most onsite wastewater systems in Nebraska are constructed under “Authorization by Rule” which does not require a construction permit from the State of Nebraska. However, some systems will require a permit as a result of the quantity or quality of the wastewater generated or site conditions that do not meet “Authorization by Rule” requirements.”
    One more reviewed finding on this topic
    • Limited — Onsite wastewater systems statewide where system size, non-domestic waste handling, or siting issues require a site-specific evaluation and permitting; ordinary systems also remain subject to applicable Title 124 compliance and registration rules.
      “Most onsite wastewater systems in Nebraska are constructed under “Authorization by Rule” which does not require a construction permit [...] However, some systems will require a permit”
  • Septic inspectionLimited

    Inspection of private onsite wastewater treatment systems statewide in Nebraska.

    • Inspection must be carried out or supervised by a certified professional, a Nebraska-licensed professional engineer, or a Nebraska-registered environmental health specialist.
    • The statute allows the Director by contract to delegate onsite wastewater inspection and registration to a governmental subdivision with a sufficiently stringent program and enforcement authority.
    “A private onsite wastewater treatment system shall not be [...] inspected [...] unless the [...] inspection [...] is carried out or supervised by either a certified professional”
  • Off-grid sanitationLimited

    A dwelling or non-dwelling generating wastewater in Butler County that is not connected to a public sewer.

    • The property must have an onsite wastewater treatment system complying with state regulations, or be connected to a public sewer system or other wastewater works.
    • Applicable registration, certification, design, and permit requirements still apply.
    • Systems receiving wastes from more than 20 persons, treating more than 1,000 gallons per day, or receiving non-domestic wastewater may be subject to Title 122 Class V injection-well requirements.

    persons served threshold for possible Title 122 requirements: > 20 persons (systems receiving wastes from more than 20 persons may be subject to Title 122 requirements) · daily treatment threshold for possible Title 122 requirements: > 1000 gallons/day (systems treating more than 1,000 gallons per day may be subject to Title 122 requirements)

    “A dwelling or non-dwelling that generates wastewater must have an onsite wastewater treatment system that complies with state regulations or be connected to a public sewer system or other wastewater works.”
    One more reviewed finding on this topic
    • Allowed (with conditions) — Off-grid wastewater sanitation using an onsite wastewater treatment system, including septic systems, holding tanks, lagoons, or mound systems, statewide in Nebraska.
      “households depend on septic systems [...] for wastewater treatment. [...] the Nebraska Department [...] regulates these systems through Title 124”
  • Well permitLimited

    Construction or modification of water wells in Nebraska groundwater management areas, on land owned or controlled by the person constructing the well.

    • Before commencing construction, the applicant must apply to the district in which the well will be located, using district forms.
    • No permit is required for test holes or dewatering wells intended for use for ninety days or less.
    • No permit is required for a single water well designed and constructed to pump fifty gallons per minute or less.
    • A district may exempt replacement water wells by rule and regulation.
    • A district may require a permit for a well designed and constructed to pump fifty gallons per minute or less when it is commingled, combined, clustered, or joined with another well or water source, excluding a water source used to water range livestock; combined wells are treated as one well and their combined capacity is used as the rated capacity.
    • In groundwater management areas where regulations have been imposed to control declining groundwater levels, a district may require permits for each well or categories of wells designed and constructed to pump fifty gallons per minute or less, except water sources required for human needs relating to health, fire control, or sanitation and water sources used to water range livestock.
    • The district must review the application and issue or deny the permit within thirty days after filing.
    • The application requires a fifty-dollar filing fee payable to the district.
    • The application must include the applicant's name and post-office address, proposed use, intended location, size, type and description, estimated depth if known, estimated capacity in gallons per minute, irrigation acreage and legal description if applicable, non-irrigation use description if applicable, replacement-well registration number if applicable, and other information required by the district.
    • A person who failed to obtain a required permit must apply for a late permit, accompanied by a two-hundred-fifty-dollar fee and the same information required for an ordinary application.
    • A person must apply before modifying a well that was previously exempt into one for which a permit would otherwise be required.

    pump capacity threshold: <= 50 gallons per minute (Single wells at or below this threshold are exempt unless a district rule requires a permit under the statutory exceptions.) · ordinary application filing fee: 50 USD (Payable to the district.) · late permit application fee: 250 USD (Applies when a required permit was not obtained.) · district decision deadline: 30 days (Measured after the application is filed.) · dewatering intended-use period: <= 90 days (Test holes and dewatering wells intended for use for ninety days or less do not require a permit.)

    “shall, before commencing construction, apply with the district in which the water well will be located for a permit on forms provided by the district”
  • Mandatory utility hookupConditional

    Wastewater service for dwellings and non-dwellings generating wastewater statewide in Nebraska.

    • The property must have an onsite wastewater treatment system complying with Title 124, or be connected to a public sewer system or other wastewater works.
    • Local city and county requirements are separate from and in addition to statewide Title 124 requirements.
    “A dwelling or non-dwelling that generates wastewater must have an onsite wastewater treatment (OWT) system [...] or be connected to a public sewer system”
  • Agricultural exemptionAvailable (with conditions)

    County zoning regulations and permit requirements for agricultural-purpose buildings on qualifying Nebraska farmsteads, and county zoning treatment of residences on farmsteads.

    • For purposes of the statute, nonfarm buildings are all buildings except buildings utilized for agricultural purposes on a farmstead of twenty acres or more that produces one thousand dollars or more of farm products each year.
    • The county board may decide whether buildings located on farmsteads used as residences are subject to county zoning regulations and permit requirements.
    • The exemption concerns county zoning and permit requirements; other applicable state, local, health, septic, floodplain, or safety requirements are not resolved by this statute.
    • The statute requires county zoning regulations to be adopted or amended only after adoption of a county comprehensive development plan and receipt of specific planning-commission recommendations.

    qualifying farmstead size: >= 20 acres (farmstead used for agricultural purposes) · annual farm products: >= 1000 USD (farmstead must produce at least this amount of farm products each year)

    “buildings utilized for agricultural purposes on a farmstead of twenty acres or more which produces one thousand dollars or more of farm products each year.”
    2 more reviewed findings on this topic
    • Conditional — State building-code applicability to construction on a farm or for farm purposes in Butler County.
      “If a county, city, or village does not adopt a code as authorized under subdivision (a) of this subsection within two years after an update to the state building code, the state building code shall apply in the county, city, or village, except that such code shall not apply to construction on a farm or for farm purposes.”
    • Available (with conditions) — Agricultural buildings on farmsteads of at least 20 acres producing at least $1,000 of farm products annually, in the context of county zoning regulations and permit requirements.
      “For purposes of this section and section 23-114.04, nonfarm buildings are all buildings except those buildings utilized for agricultural purposes on a farmstead of twenty acres or more which produces one thousand dollars or more of farm products each year.”
  • Subdividing landRegulated (with conditions)

    Subdivision in counties containing a city of the primary class, outside areas where a city or village has been granted and is exercising subdivision jurisdiction.

    • County-board approval is required before subdivision, platting, or laying out building lots and streets in the described area.
    • The county board may designate specific types of plats for approval by the county planning commission or planning director.
    • A plat has no force or effect and may not be recorded unless approved by the county board, county planning commission, or planning director.
    • The county has no power to regulate when the smallest parcel created is more than ten acres.
    • The county may prescribe subdivision standards, require installation of improvements, create public improvement districts, require a good and sufficient bond, and require dedication of land for public purposes.
    • The county planning commission approves plats on recommendation by the planning director and county engineer; the county board may withhold approval pending certified installation of required improvements, posting of a sufficient bond, or creation of public improvement districts.
    • Appeal procedures may be provided for actions of the county planning commission or planning director.

    smallest parcel exemption: > 10 acres (division is not subdivision when the smallest parcel created is more than ten acres)

    “Such a county shall have authority within the area described in this subsection (a) to regulate the subdivision of land”
    2 more reviewed findings on this topic
    • Regulated (with conditions) — Subdivision, platting, or laying out real property in building lots, streets, or other portions in unincorporated Butler County.
      “Before an owner of real property located in an unincorporated area may subdivide, plat, or lay out the real property in building lots, streets, or other portions or for the use of the purchasers or owners of lots fronting thereon or adjacent thereto, the approval of the county board is required, except that: (1) If the property is within the Niobrara scenic river corridor as defined in section 72-2006, the approval of the Niobrara Council is required; and (2) If the property is located in an area where a municipality exercises zoning control and does not require approval of the Niobrara Council, the approval of the municipality is required.”
    • Regulated (with conditions) — Subdivision, platting, or laying out real estate in counties containing a city of the primary class, outside areas where a city or village is exercising subdivision jurisdiction.
      “Such a county shall have authority within the area described in this subsection (a) to regulate the subdivision of land for the purpose, whether immediate or future, of transfer of ownership or building development, except that the county shall have no power to regulate subdivision in those instances where the smallest parcel created is more than ten acres in area,”
  • Driveway accessRequired

    New, relocated, or altered private driveways and approach roads connecting to State Highway rights-of-way in Butler County, Nebraska.

    • The rule applies to State Highway rights-of-way, not every county or municipal road.
    • Applications must use the Department form.
    • No permit will be issued where the Department has acquired all or part of the rights of access.
    • The permit must be followed; the applicant must furnish a certified check whose amount is determined after application based on the extent of proposed work.
    • Driveway construction must preserve highway drainage and the applicant must provide approved drainage structures or shallow gutters at the applicant's expense.
    “Any person desiring to construct a new driveway or approach road or any person desiring to relocate or alter an existing driveway or approach road shall apply for a permit to do so. No permits will be issued, even though application is made, for driveways or approach roads to private property along those areas where the Department has acquired all or portions of the rights of access.”
    One more reviewed finding on this topic
    • Required — New, relocated, or altered private driveways and commercial approach roads connecting to State Highway rights of way.
      “Any person desiring to construct a new driveway or approach road or any person desiring to relocate or alter an existing driveway or approach road shall apply for a permit to do so.”
  • Building in a floodplainRequired

    All development in a Nebraska floodplain, administered through applicable local floodplain programs under state and federal standards.

    • All development in a floodplain requires a permit, including additions and new structures.
    • A new structure must meet existing Base Flood Elevation requirements.
    • An addition must meet Base Flood Elevation requirements when it is a substantial improvement.
    • Substantial improvement means reconstruction, rehabilitation, addition, or other improvement costing 50 percent or more of the structure's pre-improvement market value.
    • Development includes human-made changes to improved or unimproved real estate, including construction, modifications, repairs, temporary stream crossings, roads, bridges, school buildings, storage, dredging, paving, filling, and grading.
    • Permits must ensure compliance with National Flood Insurance Program requirements, city ordinances, and county resolutions.

    substantial improvement threshold: >= 50 percent of pre-improvement market value

    “All development in a floodplain, whether an addition or a brand new structure, requires a permit.”
  • Short-term rentalsLimited

    Short-term lodging operations in Nebraska, including hotels, tourist homes, private homes rented in whole or in part, campgrounds, and RV pads or hookups.

    • A separate lodging tax permit is required for each hotel.
    • The permit is issued only after examination and approval.
    • The permit is not assignable and is valid only for the named operator, location, and transaction of business.
    • The permit must be conspicuously displayed.
    • Operating without a permit or after suspension is a misdemeanor; conviction may result in a fine up to $500 per day.
    • The cited state rule addresses lodging-tax permitting and does not establish statewide zoning approval for short-term rentals.

    maximum fine for operation without permit after conviction: <= 500 USD per day

    “Every person engaged in the business of operating a hotel in this state where the public may, for a consideration, obtain sleeping accommodations, must file an application with the Nebraska Department of Revenue for a Nebraska lodging tax permit.”
  • Permit feesPublished (with conditions)

    Nebraska DWEE air-quality construction permit applications.

    • The fee is non-refundable.
    • The fee is based on facility-wide potential to emit and the applicable pollutant thresholds.
    • Submit the fee with the completed construction permit application.
    • Payment must be by check or money order payable to the Nebraska Department of Water, Energy, and Environment; electronic payments are not currently accepted.

    fee: 250 USD (Facility-wide PTE less than 50 tons per year of any listed air pollutant, or less than 2.5 tons per year of any single HAP, or less than 10 tons per year of any combination of HAPs.) · fee: 1500 USD (Facility-wide PTE is 50 or more but less than 100 tons per year of any listed air pollutant, or 2.5 or more but less than 10 tons per year of any single HAP, or 10 or more but less than 25 tons per year of any combination of HAPs.) · fee: 3000 USD (Facility-wide PTE is 100 tons or more per year of any listed air pollutant, or 10 tons or more per year of any single HAP, or 25 tons or more per year of any combination of HAPs.)

    “Chapter 3, Section 002.01 of Nebraska Administrative Code Title 129 – Nebraska Air Quality Regulations requires that each air quality construction permit application be accompanied by a non-refundable fee.”
  • county zoning authorityGeneral

    Nebraska county boards adopting zoning resolutions for county territory outside incorporated cities and villages and outside areas where a city or village has been granted or ceded zoning jurisdiction and is exercising that jurisdiction.

    • The county board may adopt a zoning resolution having the force and effect of law.
    • The zoning resolution may regulate buildings, structures, lot coverage, setbacks, yards, population density, building uses, and land uses for agriculture, forestry, recreation, residence, industry, and trade in the unincorporated area of the county.
    • The powers may not be exercised within incorporated cities or villages or within an unincorporated area over which a city or village has been granted or ceded zoning jurisdiction and is exercising it.
    • A city or village zoning ordinance or amendment controlling an unincorporated area supersedes the county resolution or regulation.
    • If a zoning resolution or regulation affects the Niobrara scenic river corridor, the Niobrara Council must act as provided in section 72-2010.
    • A county board may not prohibit a qualifying manufactured home solely because it is manufactured, but may impose the listed installation and design standards and may not impose additional standards unless uniformly applied to all single-family dwellings in the zoning district.
    • Special districts or zones may be established in areas subject to seasonal or periodic flooding.
    “to adopt a zoning resolution, which shall have the force and effect of law;”
  • county building authorityGeneral

    Nebraska counties adopting, administering, enforcing, and requiring permits under local building or construction codes for buildings, including residential construction, in unincorporated areas.

    • A county may enact, administer, or enforce a local building or construction code only if it adopts the state building code or adopts a building or construction code that conforms generally with the state building code.
    • A local code may include special or differing standards only within the statutory conformity rules, including standards addressing construction costs, safety, durability, efficiency, best practices, or special local conditions.
    • A local code must be regularly updated; generally, the most recently enacted state building code or a conforming code must be adopted within two years after an update to the state building code.
    • If a county does not adopt a code as authorized within two years after an update to the state building code, the state building code applies in the county, except that it does not apply to construction on a farm or for farm purposes.
    • A county may adopt administrative amendments concerning enforcement organization, staff qualifications, plan examination, inspections, appeals, permits, and fees, and may publish those amendments separately from the code.
    • Under section 23-172, county-adopted codes and the building-permit or occupancy-permit requirements imposed by those codes or sections 23-114.04 and 23-114.05 apply throughout the county except within incorporated cities or villages and except within an unincorporated area where a city or village has been granted zoning jurisdiction and is exercising that jurisdiction.
    • Under section 23-114.04, permits are required before erection, construction, reconstruction, alteration, repair, or conversion of a nonfarm building or structure within a zoned area; a permit may be withheld when the proposed purpose conflicts with applicable district zoning regulations.
    • Section 23-114.04 permits reasonable county permit-fee schedules and requires written plans, including sanitation, plumbing, and sewage-disposal information, that fully conform to zoning regulations before permits issue.
    • Section 23-172 states that nothing in that section creates an obligation for the county to inspect plumbing work to determine compliance with the plumbing code.
    “Any county, city, or village may enact, administer, or enforce a local building or construction code if or as long as such county, city, or village: (i) Adopts the state building code; or (ii) Adopts a building or construction code that conforms generally with the state building code.”

Set by your township or city, not the county

In Nebraska, zoning is adopted by each township or city, so Butler County has no county-wide answer on these. Find your township or city in the list of places on this page, or call its clerk or zoning administrator.

  • Living in an RV
  • Manufactured homes
  • Accessory dwellings

Still unanswered

We looked and could not find an official answer yet. Silence is not permission — ask the county directly.

  • Inspections — Building inspections for residential construction in unincorporated Butler County.
  • Certificate of occupancy — Certificates of occupancy for residential buildings in unincorporated Butler County.

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Living off-grid in Butler County, Nebraska

Is Butler County a good place to live off-grid or homestead?

Butler County scores 44/100 on the Bolthole Index, a marginal county profile. Its strengths: low administrative friction for a quiet rural property and manageable long-term carry cost. Watch-outs: workable self-sufficiency basics (29.6″/yr rainfall) and elevated current hazard exposure.

Do you need a building permit in Butler County, Nebraska?

Butler County does not require a county building permit for a home in unincorporated areas, and it has no county-wide zoning. Onsite septic is permitted by Nebraska Department of Environment and Energy (NDEE / DWEE) Onsite Wastewater Program. Owner-builders may act as their own contractor to build their home. These answers are quoted from official sources and independently re-checked. Rules change and cities within the county differ — always confirm with the county before you buy or build.

How much does land cost in Butler County, Nebraska?

Land in Butler County runs about $6,462 per acre, based on the latest county data.

What is the water situation in Butler County?

Butler County gets about 29.6" of rain a year, with severe drought in roughly 17.6% of years.

How remote is Butler County?

A representative private-land location has about 29,784 people within a 30-minute drive and 1,845,725 within two hours. The road-network catchments count population across county lines and clusters of smaller cities; straight-line radius values remain available as a comparison.