Unincorporated Custer County, Nebraska requires a county zoning permit before a house or other structure is erected, moved, enlarged or structurally altered1. County zoning applies outside municipal zoning jurisdiction; the Village of Arnold has its own zoning23. Nebraska administers septic requirements, with separate local approvals possible45. A new or changed use needs a Certificate of Zoning Compliance before occupancy6.
At a glance
- Building permit
- A county zoning permit is required before construction or moving a structure1
- Zoning
- Yes, throughout the unincorporated county area7
- Septic
- Nebraska handles septic; registration and applicable state and local approvals are required4895
- Floodplain
- County approval is required before a zoning permit for floodplain development10
- RV living
- RV-park stays are seasonal; ordinary private-parcel occupancy remains unconfirmed1112
- Tiny home
- Allowed by type, with county siting and design conditions13
- Permit fee
- $50 for a zoning permit or certificate of compliance on the published fee page14
- Septic soils
- About 21.8% are rated without severe limits for a conventional drain field15
Who to call
Zoning
Custer County Planning and Zoning
Zoning permits, zoning and conditional-use review, subdivision review, and county floodplain approval
431 S 10th, Broken Bow, NE 68822
Septic permits
Nebraska Onsite Wastewater Program
Statewide onsite wastewater standards, registration, professional certification, subdivision review and site-specific permits
245 Fallbrook Blvd., Suite 100, Lincoln, NE 68521
Contact details are copied from each office’s official page and were checked against it on October 12, 2026.
Off-grid gear
Going off-grid in Custer County means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Custer County, Nebraska?
Yes. Rural construction must start with county zoning approval: Custer County requires a zoning permit before a building or structure is erected, moved, enlarged or structurally altered1. The Nebraska state building code applies when the county has not adopted a qualifying local code, with a farm-purpose exception; we could not confirm a separate county code adoption or routine inspection program1612. Development in a regulated floodplain needs county approval before the zoning permit can issue17. A new or changed use cannot be occupied until the Zoning Administrator issues a Certificate of Zoning Compliance, unless an authorized appeal, variance or conditional use provides otherwise6.
Who handles Custer County building and zoning permits?
Custer County Planning and Zoning is the first stop because the office evaluates zoning and conditional-use permits, reviews subdivisions and administers county zoning12. Call (308) 872-2410, email zoning@custercountyne.gov, or visit 431 S 10th in Broken Bow, Nebraska12. Permit forms are available at the Zoning Office in the Custer County Courthouse18. The application calls for a plot plan and project details including lot dimensions, parking, water supply, sewage disposal, erosion control, soil conditions and permeability19. The published fee page lists $50 for a zoning permit or certificate of compliance and $25 for a floodplain-development application, but gives no effective date14. Ask Planning and Zoning to confirm the current fee and every required review before filing12.
Does Custer County have zoning?
Yes. Custer County administers zoning throughout the unincorporated county, except where municipal annexation or municipal zoning jurisdiction displaces county authority72. Village of Arnold has its own zoning; Nebraska onsite-wastewater requirements still apply, and Arnold requires a Village Superintendent permit before private sewage-system construction when public sewer is unavailable3420. The published county districts are AG-G, AG-T, AH, VAD and WP, with an official zoning map adopted as part of the resolution21. Agricultural district tables include road-centerline, side, rear and height limits, but parcel overlays and use-specific rules may differ2223. Unincorporated Custer County allows one accessory dwelling per lot in districts identified by the land-use matrix, subject to a conditional-use permit, shared access, district setback and height limits, and generally shared utilities24. The owner must live on the property and file a deed restriction prohibiting separate ADU sale before the ADU zoning permit24. Short-term rentals are limited to a primary residence or an accessory dwelling on the same property, exclude multifamily and party rentals, and require applicable lodging taxes and life-safety compliance25.
How do septic permits work in Custer County?
Nebraska's Onsite Wastewater Program administers septic requirements in Custer County, but local requirements may be separate from state Title 124 approval45. Inside Arnold, private sewage-system construction when public sewer is unavailable also needs a written permit signed by the Village Superintendent20. Construction, reconstruction, alteration, modification or a non-exempt repair must follow the state process: qualifying systems may use general-permit coverage, while systems outside that coverage need a construction permit before work and an operating permit before use9. New or changed systems must also be registered with the state8. A dwelling that generates wastewater must use a compliant onsite system, connect to public sewer or use other wastewater works; the wastewater rule does not cover electric or natural-gas hookups26. Subdivision review applies when onsite wastewater is proposed on a lot smaller than three acres27. Call the Nebraska Onsite Wastewater Program at (402) 471-4285 or email DWEE.onsite@nebraska.gov28. Only about 21.8% of county soils are rated without severe limitations for a conventional drain field, so arrange a site evaluation before buying15.
Can you live in an RV or tiny home in Custer County?
Custer County allows tiny houses by type, subject to county rules13. A site-built tiny house needs a habitable room of at least 120 square feet, other habitable rooms of at least 70 square feet except kitchens, required facilities, utilities, egress and a foundation; it cannot be built in a floodplain13. An RV, park-model or camper type must be 400 square feet or less, retain its wheels and axles, remain towable or self-propelled, and serve as temporary living quarters13. In a county-regulated RV park or campground, an RV or trailer may be occupied for no more than four continuous months in a 12-month period and may remain afterward only in storage11. That park rule does not settle RV occupancy on an ordinary private parcel, so ask Custer County Planning and Zoning before planning to live in one during construction12.
Building a home in Custer County: the steps, in order
- Ask Custer County Planning and Zoning to confirm jurisdiction, the zoning district, allowed use, exact setbacks and subdivision review22129.
- Confirm legal access; a new, moved or altered driveway connecting to a state-highway right of way requires a Nebraska permit30.
- Check the floodplain before siting improvements because County Floodplain Administrator approval must precede a zoning permit there17.
- Prepare the plot plan and required water, wastewater, parking, erosion and soil information19.
- Submit the county zoning application before erecting, moving, enlarging or structurally altering the house1.
- Arrange a compliant wastewater system, registration and any required state permits931.
- Obtain the Certificate of Zoning Compliance before occupancy6. An owner working on the owner's property is exempt from contractor registration, not from project approvals32.
What should you check before buying land in Custer County?
Confirm the zoning district and jurisdiction with Custer County Planning and Zoning before relying on a listing's description of allowed use212. Check the building site against floodplain mapping because regulated floodplain development needs county approval before the zoning permit17. Order a parcel-specific septic evaluation because only about 21.8% of county soils are rated without severe limitations for a conventional drain field15. For a private well, Nebraska lists a $240 registration fee for a single well pumping no more than 50 gallons per minute; a well pumping more than 50 gallons per minute has a $280 registration fee and may also need a local Natural Resources District permit33. Verify legal road access separately because a state-highway driveway requires state approval, while we could not confirm a general county-road driveway permit3012.
Watch-outs
- Custer County calls its required construction approval a zoning permit; we could not confirm a separate residential building-code permit or routine inspection program, so ask Planning and Zoning what applies112.
- Floodplain approval comes before the zoning permit when the proposed site is in a regulated floodplain17.
- State septic approval does not replace separate local requirements; Arnold requires a Village Superintendent permit before private sewage-system construction when public sewer is unavailable520.
- The seasonal RV limit applies to county-regulated parks and campgrounds; ordinary private-parcel RV occupancy and county-road driveway approval remain unconfirmed, so ask Custer County Planning and Zoning1112.
Sources
- Planning and Zoning – Custer County, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Village of Arnold: Chapter 153: Zoning (Custer County), quoted and re-checked
- Onsite Wastewater Program, quoted and re-checked
- Owner Construction/Operating Permit Checklist, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Planning and Zoning – Custer County, quoted and re-checked
- Onsite Wastewater Program, quoted and re-checked
- Title 124 Onsite Wastewater Treatment Systems, quoted and re-checked
- custercountyne.gov, quoted and re-checked
- custercountyne.gov, quoted and re-checked
- Custer County Planning and Zoning (custercountyne.gov)
- Custer County Zoning Regulations, quoted and re-checked
- Zoning Fees – Custer County, quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- Nebraska Revised Statute 71-6403 — State building code; adopted; amendments, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Planning and Zoning – Custer County, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Village of Arnold: §§ 53.025–53.029 Private Sewage Disposal (Custer County), quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Custer County Zoning Regulations, quoted and re-checked
- Onsite Wastewater Program, quoted and re-checked
- Planning and Zoning – Custer County, quoted and re-checked
- Nebraska Onsite Wastewater Program (dwee.nebraska.gov)
- Planning and Zoning – Custer County, quoted and re-checked
- Title 410, Chapter 2 - Driveway and Approach Road Permits (Nebraska statewide rule), quoted and re-checked
- Onsite Wastewater Program, quoted and re-checked
- Nebraska Revised Statute 48-2104 — Registration required (Nebraska statewide rule), quoted and re-checked
- Landowners/Public – DWEE Nebraska, quoted and re-checked
Written October 12, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.